Refinery - II M&I SD Oct-Nov 2018
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Chennai Petroleum Corporation Limited (A group company of Indian Oil)<br />
Technical - Inspection<br />
Chennai Petroleum Corporation Limited (A group company of Indian Oil)<br />
Technical - Inspection<br />
1.7 Key Positive Points / Achievements:<br />
1.7.1 All major maintenance contracts were awarded 3 to 4 months before the start of shutdown and<br />
contractors were well mobilized in advance and most of pre-fabrication activities were completed before<br />
the start of shutdown.<br />
1.7.2 All critical activities in CDU-2 & FCCU were clubbed together and awarded as a Super critical work<br />
contract to a leading Indian mechanical contractor well in advance providing 75 days for mobilization &<br />
pre-fabrication. Most of the critical FCCU R-R precision items were pre-fabricated in world class<br />
workshop @ L & T, Hazira.<br />
1.7.3 Initially, it was planned to replace the entire CO Boiler convection section in position (Involving removal &<br />
refixing of tubes, tubesheets, casing on all sides with castable refractory lining) during planning stage,<br />
but the decision to pre-fabricate & replace CO Boiler convection section in 3 modules (which were prefabricated<br />
in 80 days at site) reduced not only time outage, but also ensured quality of work. During<br />
dismantling, it was observed that convection section was totally crumbled / jammed with refractory, tubes<br />
& tubesheet and the decision of pre-fabricating & replacing in modules really saved huge time. In<br />
position replacement during shutdown would have taken not less than 100 engg. days.<br />
1.7.4 Keeping a spare regenerator cyclones for M & I was decided & procurement initiated two and half years<br />
prior to shutdown but had to be cancelled prior to PO issuing stage. But, an idle shutdown outage<br />
opportunity was utilized to identify the extensive damages inside the cyclones and procurement action<br />
initiated again & got delivered 7 months before the start of shutdown.<br />
1.7.5 All exchangers / coolers which had isolation facility to be released on the run were released for<br />
maintenance & taken up as pre-shutdown activity. In total 39 nos. of exchangers/coolers were completed<br />
out of 48 nos. ahead of start of shutdown, therby reducing considerable volume of work during shutdown<br />
outage. 15 nos. of exchangers/coolers retubing was completed prior to M&I shutdown.<br />
1.7.6 To facilitate replacement of intermediate tubesheet & convection refractory lining in 16-F-01 Charge<br />
heater, it was a good decision to pre-fabricate entire convection in a single module involving 260 nos.<br />
alloy steel weld joints. This also reduced considerable no. of days during shutdown.<br />
1.7.9 Due to pre-mature failure & leaks in 15-F-01A APH, bottom two modules were redesigned & replaced.<br />
Bottom most module was designed with Glass tubes and the performance & longevity need to be<br />
monitored.<br />
1.7.10 Replacement of Flare tip, molecular seal, water seal drum and flare stack were done using an exclusive<br />
400 T crane unlike the previous shutdowns when the same were done using derric winch mechanism<br />
causing delays in dismantling the equipment.<br />
1.7.11 Painting of flare derrick structures using rope access method yielded good results but, no. of trained<br />
personnel to be spelt out & increased considerably.<br />
1.7.12 Close Proximate Radiography Testing was deployed for CO Boiler and critical R-R circuit jobs which<br />
ensured better productivity during pre-fabrication & site work.<br />
1.7.13 In-situ machining of 96 inch dia. Regenerator manway flanges done for first time & yielded leak free<br />
condition after start up.<br />
1.7.14 Replacement of Riser Wye section was done for the first time in a very professional way in the congested<br />
R-R circuit area.<br />
1.7.15 Replacement of more than 70% fin fan coolers which are recommended for retubing saved lot of time<br />
during maintenance outage.<br />
1.7.16 There were very minimum weld defects observed in RT of critical jobs (viz.) R-R circuit, CO Boiler, 16-F-01<br />
Charge heater, 15-F-01A Atmospheric heater, 15-F-02A Vacuum heater, 15-C-15 vacuum column top dish<br />
weld joint considering the volume of welding involved in CS, AS & SS material category.<br />
1.7.17 Bundles were pulled out in a very safe manner, wherever bundle pullers were used and may have to be<br />
maximized in future for usage wherever feasible.<br />
1.7.18 The quality of retubing work with proper tools like tube pullers, expanders, drilling machines, etc., paid off<br />
good results during hydro testing. M/s. Arudra Engg. demonstrated good execution of retubing with no<br />
damage to tubesheet expansion grooves during the exercise.<br />
1.7.19 The quality of paining work done in R-R circuit & 15-C-15 was extremely good with proper surface<br />
preparation during the shutdown outage.<br />
INSPECTION EXECUTIVE SUMMARY<br />
1.7.7 Pre-fabrication of 15-F-02A radiant casing panels along with refractory anchoring and carrying out<br />
mechanical decoking expedited maintenance work during shutdown outage.<br />
1.7.8 Though there was resistance to permit replacement of 15-F-01A APH modules (bottom 2 modules) on the<br />
run, the replacement was done to precision by M/s.L & T a couple of weeks before the start of shutdown<br />
and this has reduced a huge amount of work load during the shutdown outage. Replacement of common<br />
APH modules for Ref-3 heater (201-F-01/02) during plant operation was also reviewed by engaging a<br />
structural consultant along with M/s.L & T, but it was concluded that the same can be taken only during a<br />
shutdown outage due to space constraints.<br />
1.7.20 The Quality control (QC) team engaged by the maintenance contractors play a major role to ensure Quality<br />
& to eliminate defects / rejection and inturn improve productivity during M&I shutdowns. M/S L&T<br />
exhibited a elaborate & a qualified set up with all required NDT tools for their complete scope of work and<br />
the QC team had a detailed plan worked out in the pre-shutdown stage itself. & well aware of the<br />
complete shutdown scope and offered all QC requirements as per codes & standards.<br />
60<br />
<strong>Refinery</strong> - <strong>II</strong> M&I S/D <strong>Oct</strong>-<strong>Nov</strong> <strong>2018</strong> - Inspection Report<br />
<strong>Refinery</strong> - <strong>II</strong> M&I S/D <strong>Oct</strong>-<strong>Nov</strong> <strong>2018</strong> - Inspection Report<br />
61