Refinery - II M&I SD Oct-Nov 2018
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Chennai Petroleum Corporation Limited (A group company of Indian Oil)<br />
Technical - Inspection<br />
Chennai Petroleum Corporation Limited (A group company of Indian Oil)<br />
Technical - Inspection<br />
machineries & a meticulous plan. The anticipated job scope in R-R circuit was found to be almost in line with<br />
requirement after equipment opening and considerable replacement of heater tubes were reduced from the<br />
planned scope of work. It appears that the scheduled no. of engg. days (28 days) as per standard guidelines were<br />
are not reviewed further in line with the extensive scope of work planned this time, especially when multiple<br />
agencies had to perform with heavy machineries around R-R circuit & CO Boiler. It was felt that the no. of days<br />
scheduled is not practical enough to complete the scope of work in critical equipments.<br />
Though FCCU work was scheduled for a total of 33 days, actual completion of work witness with respect to type of<br />
equipments is tabulated as below:-<br />
Type of Eqpt.<br />
Handing over of last Equipment<br />
S/D day of<br />
Completion<br />
R-R Circuit Riser Bottom manway box up 38 th day<br />
CO Boiler Comb. chamber manway box up 38 th day<br />
FCCU Charge Heater Box up of floor manway 38 th day<br />
Though CDU-2 work was scheduled for a total of 30 days, actual completion of work witnessed with respect to<br />
type of equipments is tabulated as below:-<br />
Type of Eqpt.<br />
Handing over of last equipment<br />
S/D day of<br />
Completion<br />
15-F-01A Manway boxup 35 th day<br />
15-F-01B Manway boxup 36 th day<br />
15-F-02A Manway boxup 36 th day<br />
15-F-02B Manway boxup 36 th day<br />
Columns / Vessels 15-C-05 (Kero Stripper) boxup 37 th day<br />
Heat Exchangers 15-E-111A/B 38 th day<br />
Piping Modification 2” velocity line provision in 15-F-02B 39 th day<br />
Piping Replacement<br />
2” stabiliser naphtha from 15-E-18A/B shell O/l to FCC riser<br />
(2”-P-15-4215-A1A)<br />
41 st day<br />
INSPECTION EXECUTIVE SUMMARY<br />
CO Stack Bottom door box up 37 th day<br />
Columns / Vessels 16-C-01 Main column / 16-C-59 (Debutaliser) 38 th day<br />
Heat Exchangers 16-E-251A/B 33 rd day<br />
Piping Modification<br />
Piping Replacement<br />
Routing of Raw Oil for 16-G-102A/B Seal flushing<br />
(16-C-25187 R.0)<br />
2” Net liquid pipeline from WGC-I to WGC-<strong>II</strong><br />
(9910-016-005-<strong>2018</strong>)<br />
32 nd day<br />
37 th day<br />
In line with handing over of major equipment, piping modification & replacement work had to be trimmed in the<br />
fag end of shutdown including waiving of few NDT requirements and deferring a few due to paucity of time.<br />
1.6.3.2 CDU-2 :<br />
During the planning stage, it was well thought that the major Atmospheric & Vacuum heaters 15-F-01A & 02A<br />
under critical path along with 15-C-15 Vacuum column top dished end replacement. Out of the above, it was very<br />
clear that the total outage had to be decided based on 15-F-02A heater due to complete radiant refractory<br />
replacement along with casing and a activity based time schedule should have been made to arrive the no. of<br />
engg. days. But, it appears that the scheduled no. of engg. days (25 days) as per standard guidelines was not<br />
reviewed further in line with the extensive refractory & other scope of work including additional days for<br />
decontamination & dry out. It was felt that the no. of days scheduled is not practical enough to complete the<br />
extensive scope of work in critical equipment (vis.) 15-F-02A heater with complete radiant refractory replacement<br />
including casing along with changing of convection intermediate tubesheets involving considerable Alloy steel<br />
welding / NDT requirements.<br />
In line with handing over of major equipment, piping modification & replacement work had to be trimmed in the<br />
fag end of shutdown including waiving of few NDT requirements and deferring a few due to paucity of time.<br />
1.6.3.3 Wax & Propylene :<br />
There was no major critical works planned in Wax & Propylene units other than routine maintenance work and<br />
anticipated repairs / replacement. Both the units were scheduled for a total of 30 days, but the actual completion<br />
of work witnessed with respect to type of equipments is tabulated as below:-<br />
Type of Eqpt.<br />
Handing over of last Equipment<br />
S/D day of<br />
Completion<br />
14-F-01 Manway boxup 35 th day<br />
14-F-101 Manway boxup 20 th day<br />
Columns / Vessels<br />
Heat Exchangers<br />
Piping Modification<br />
Piping Replacement<br />
14-C-15 (Inert gas holder)<br />
19-C-01<br />
14-E-65A/B/C (R22 Condenser)<br />
19-E-02A /04<br />
Mass flow meter for FO Supply & Return line in 14-F-01(14-D-25317<br />
R.1)<br />
19-E-05 tube side I/L & O/L-BV Provision for isolation purpose & PT<br />
provision for monitoring (19-C-25457)<br />
14-T-1hot solvent gut wash 2” (9910-014-008-2016)<br />
17 th day<br />
40 th day<br />
35 th day<br />
36 th day<br />
32 nd day<br />
36 th day<br />
33 rd day<br />
2” FG header take off to 19-C-5 (9910-019-004-<strong>2018</strong>) 35 th day<br />
In line with handing over of major equipment, piping modification & replacement work had to be trimmed in the<br />
fag end of shutdown including waiving of few NDT requirements and deferring a few due to paucity of time.<br />
54<br />
<strong>Refinery</strong> - <strong>II</strong> M&I S/D <strong>Oct</strong>-<strong>Nov</strong> <strong>2018</strong> - Inspection Report<br />
<strong>Refinery</strong> - <strong>II</strong> M&I S/D <strong>Oct</strong>-<strong>Nov</strong> <strong>2018</strong> - Inspection Report<br />
55