04.01.2013 Views

Section 3.10: Site Plans and Technical Data - Rick Neufeld Comments

Section 3.10: Site Plans and Technical Data - Rick Neufeld Comments

Section 3.10: Site Plans and Technical Data - Rick Neufeld Comments

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Northern Gateway Pipelines Inc.<br />

<strong>Section</strong> <strong>3.10</strong>: <strong>Site</strong> <strong>Plans</strong> <strong>and</strong> <strong>Technical</strong> <strong>Data</strong><br />

Table of Contents<br />

Of particular importance for the marine structure foundation design is the stability of the steep underwater<br />

rock slopes, as well as the stability of the clay <strong>and</strong> rock slopes along the foreshore above the marine<br />

structures. Oriented rock core techniques <strong>and</strong> geological mapping of the rock structure will be used to<br />

evaluate the nature <strong>and</strong> extent of joints <strong>and</strong> faults in the rock to help assess the rock stability. The results<br />

of this investigation will dictate the possible structure types <strong>and</strong> construction methods required to mitigate<br />

the risk of rock slope failure.<br />

2.6.2 Upl<strong>and</strong>s Geotechnical Investigations<br />

Although there has been no marine geotechnical investigations conducted for the berth structures to date,<br />

some useful information can be obtained from a two-phase preliminary-level geotechnical investigation<br />

that was completed for the upl<strong>and</strong>s portion of the terminal site (Reference 5, 6). This study included<br />

LiDAR elevation data, boreholes, <strong>and</strong> geophysical data <strong>and</strong> was meant to characterize the geological<br />

conditions of the upl<strong>and</strong>s site. The goal was to provide preliminary geotechnical assessments <strong>and</strong><br />

recommendations relative to the site grading <strong>and</strong> foundation design options for the terminal tank farm <strong>and</strong><br />

other upl<strong>and</strong> facilities.<br />

The upl<strong>and</strong>s geotechnical investigation included:<br />

• A ground-based survey carried out at the site during September <strong>and</strong> October of 2005 under the<br />

direction of AMEC. This survey was done to establish a project control network <strong>and</strong> provide<br />

geophysical line profile data for concurrent geophysical surveying;<br />

• Additional ground-based surveys in July <strong>and</strong> August of 2006, including 52 h<strong>and</strong>-cut survey lines<br />

totalling approximately 20.2 km in plan length. The line locations were selected to provide a grid of<br />

data across the entire site, including the main tank lot, the impoundment reservoir area, the main<br />

terminal facilities area, <strong>and</strong> the foreshore area;<br />

• A LiDAR survey completed in September of 2005. The survey was helicopter based <strong>and</strong> was carried<br />

out at planned flight altitudes of between 100 metres <strong>and</strong> 250 metres above ground level. The original<br />

LiDAR data did not correlate well with the ground-based surveys therefore the LiDAR was<br />

subsequently re-flown in 2006. The second set of LiDAR data aligned very well with the groundbased<br />

surveys;<br />

• Seven drill holes <strong>and</strong> nine test pits completed at the site between October <strong>and</strong> November of 2005. The<br />

holes were drilled to between 1.5 metres <strong>and</strong> 3.0 metres into the underlying bedrock, resulting in total<br />

borehole depths between 10.2 metres <strong>and</strong> 21.8 metres. The test pits were completed to depths ranging<br />

between 1.0 metres <strong>and</strong> 7.5 metres depth;<br />

• An additional 17 drill holes completed on the site between July <strong>and</strong> August 2006. Boreholes were<br />

drilled 5.0 metres into bedrock, resulting in total borehole depths between 5.2 metres <strong>and</strong><br />

33.2 metres. Four of the drill holes were drilled using diamond drilling methods to investigate<br />

bedrock conditions. Final depths for these holes ranged between 42 metres <strong>and</strong> 97.2 metres;<br />

• Initially, 11 geophysics survey lines (totalling 11.6 km in plan length) surveyed using seismic<br />

refraction geophysical methods to estimate the depth of overburden soils <strong>and</strong> to provide a profile of<br />

the underlying bedrock surface along the lines; <strong>and</strong>,<br />

Page 2-18 FINAL - Rev. 0 January 20, 2010

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!