Cement Internal Development Plan<br />
Careful Phasing of New Capacities Start Up<br />
� Initial plan: 60 MT planned by <strong>the</strong> end of 2010<br />
� Revised plan: 38 MT will have started by end of 2010<br />
* Group share<br />
MT<br />
� Of which 15 MT already started at <strong>the</strong> end of 2008<br />
48 MT will be operating in 2012<br />
New capacities schedule 2009-2011<br />
13<br />
9<br />
26<br />
14<br />
2009 2010 2011<br />
Capex: ~ €2Bn * <strong>to</strong> spend over 2009-2011<br />
10<br />
Initial plan<br />
Revised plan