8.3 Electrical connections<br />
8.3.1 Before connecting the power cables to line input terminals L1-N, ensure that the main switch on the power<br />
distribution panel is in OFF position (O), and that no one can switch on the power accidentally.<br />
8.3.2 Scrupulously observe all the regulations in force concerning safety and accident prevention.<br />
8.3.3<br />
Ensure that all the terminals are fully tightened, paying particular attention to the earth terminal.<br />
8.3.4 Connect the cables to the terminal board as indicated in the wiring diagrams given in the enclosed booklet.<br />
8.3.5 Check that all the connecting cables are in excellent condition, with the external sheathing unbroken.<br />
8.3.6 Check that the differential switch that protects the system is of the right size.<br />
Provide automatic protection of the supply line against short circuits by means<br />
of the Curve C 16A Automatic Switch for panel type <strong>ED</strong> 1,3 M and 20 A for<br />
panel type <strong>ED</strong> 3 M, <strong>ED</strong> 3 M <strong>HS</strong>.<br />
8.3.7 The apparatus must be correctly and safely earthed as required by the<br />
regulations in force.<br />
8.3.8 Depending on the type of installation, limit the maximum length of the power cable as follows:<br />
Panel model Max. line length ( m )<br />
( section 1.5 mm 2 Max. line length ( m )<br />
) ( section 2.5 mm 2 Max. line length ( m )<br />
)<br />
( section 4 mm 2 )<br />
<strong>ED</strong> 1,3 M 15 30 45<br />
<strong>ED</strong> 3 M 10 20 30<br />
<strong>ED</strong> 3 M <strong>HS</strong> 10 20 30<br />
8.3.9 Instrumental checks to be carried out by the installer:<br />
a) continuity of the protection leads and of the main and supplementary equipotential circuits;<br />
b) insulation resistance of the electric system;<br />
c) test efficiency of the differential protection;<br />
d) test the applied voltage;<br />
e) test operation as indicated in point 8.5.<br />
8.4 Supplying power to the control panel<br />
After having correctly performed the steps described above, close the inner door of the panel, tightening the three<br />
screws provided, turn the magnetothermal switch ref. QM1 to position 0. Supply power to the control unit, switching on<br />
the main switch on the distribution panel. Turn on the isolating switch ref.. QS1. The electropump is not fed.<br />
8.5 Starting the system<br />
1. Ensure that the external commands (floats or thermostats) are in OFF position (command excluded).<br />
2. Press the button ref.SB1 in MAN position. The electropump is fed as long as it is held down.<br />
�� For systems with one float the start command is given by the float ref. A (the float ref. B must be jumped.<br />
�� For systems with two floats, the start command is given by the maximum level float (connected to the terminals<br />
ref. B) and the stop command by the minimum level float (connected to the terminals ref.A).<br />
Avoid starting the system, turning the isolating switch (ref. QS1) with the switch ref.<br />
QM1 in position I.<br />
8.6 Alarm system<br />
1. Check correct operation of the alarm float connected to the terminals ref. P (n°25-26).<br />
2. With the alarm float in ON position check correct operation of the remote alarm connected to the terminals Q<br />
(n°31-32), remembering that the contact as supplied in the standard version has no potential.<br />
N.B.: The feeding circuit of the alarm system must be provided with a PELV safety circuit (CEI<br />
EN 60204-1). Otherwise, ensure that the earth lead of the float is connected to the terminal<br />
8.7 Using the panel to feed in-line circulating pumps<br />
<strong>ED</strong> 1,3 M:<br />
- Connect the circolator in L1-N of P1<br />
- Make bridge 3-4 of B<br />
- Connect the thermostat in 1-2 of A<br />
<strong>ED</strong> 3 M:<br />
- Connect the circolator in C-P of P1<br />
- Make bridge K-K of P1<br />
- Make bridge 3-4 of B<br />
- Connect the thermostat in 1-2 of A<br />