Specification 12 <strong>Hot</strong> <strong>Rolled</strong> <strong>Asphalt</strong> <strong>and</strong> <strong>Macadam</strong> for Airfields 7 Plant <strong>and</strong> Workmanship<br />
cuts extending to the full depth <strong>of</strong> the surface<br />
course.<br />
7.7.4 All loose <strong>and</strong> crumbling fractions shall be<br />
removed from the bottom <strong>and</strong> sides <strong>of</strong> the trench.<br />
The bottom <strong>and</strong> sides shall be completely painted<br />
with tack coat.<br />
7.7.5 The defective surfacing shall be replaced<br />
with the specified surface course material. It shall<br />
be placed in the trenches in lifts <strong>of</strong> about 50 mm<br />
each which shall be compacted separately with<br />
approved mechanical or h<strong>and</strong> tampers as specified<br />
in Clauses 7.15 <strong>and</strong>/or 7.16.<br />
7.7.6 At the time <strong>of</strong> compaction, the mixture shall<br />
be at the specified temperature. The final layer<br />
shall be laid so as not to leave a concave finish<br />
below the general surface after thorough<br />
compaction by rolling.<br />
7.7.7 All loose material shall be removed from<br />
any potholes, the bottom <strong>and</strong> sides <strong>of</strong> the<br />
depressions painted with tack coat <strong>and</strong> then the<br />
potholes backfilled, compacted <strong>and</strong> finished in<br />
accordance with sub-Clauses 7.7.5 <strong>and</strong> 7.7.6.<br />
(NOTE. Further guidance on making good is given in DE<br />
Functional St<strong>and</strong>ard 06, “Guide to Airfield Pavement<br />
Maintenance”.)<br />
7.8 TRANSPORTING PLANT MIXTURES<br />
7.8.1 The plant mixtures shall be transported<br />
without delay to the laying sites from the mixing<br />
plant or from hot storage bins taking care to prevent<br />
segregation. The vehicles shall be double sheeted<br />
during transit <strong>and</strong> while waiting to prevent loss <strong>of</strong><br />
heat, contamination <strong>and</strong> wetting. All vehicles shall<br />
be mechanically sound <strong>and</strong> shall be suitable for the<br />
spreading equipment in use <strong>and</strong> shall have<br />
insulated bodies.<br />
7.8.2 The use <strong>of</strong> water or proprietary products on<br />
the surfaces <strong>of</strong> the transporting vehicles to facilitate<br />
discharge shall be strictly regulated to the absolute<br />
minimum. If the Project Manager considers that<br />
contamination <strong>of</strong> the mixtures is occurring, the<br />
vehicle shall be thoroughly cleaned out to his<br />
satisfaction before being used again. The use <strong>of</strong><br />
diesel oil, dust, s<strong>and</strong> or other fine particles is<br />
prohibited.<br />
7.8.3 The temperature <strong>of</strong> the load in every<br />
transporting vehicle shall be checked in accordance<br />
with BS EN 12697-13 whilst discharging from the<br />
delivery lorry into the paver hopper. If the<br />
temperature <strong>of</strong> any batch is below the minimum<br />
delivery temperature specified in Clause 4.6 for <strong>Hot</strong><br />
<strong>Rolled</strong> <strong>Asphalt</strong>, Clause 5.3 for <strong>Asphalt</strong> <strong>Concrete</strong><br />
(<strong>Macadam</strong>) or Clause 6.5 for Pervious <strong>Macadam</strong>,<br />
the load shall be rejected <strong>and</strong> shall be removed<br />
from site immediately. If the delivery temperature <strong>of</strong><br />
Pervious <strong>Macadam</strong> is greater than 100 °C when<br />
160/220 paving grade bitumen has been used, or<br />
greater than 120 °C if modified 160/220 paving<br />
grade bitumen has been used, the load shall be<br />
rejected <strong>and</strong> shall be removed from site<br />
immediately.<br />
7.8.4 Each delivery <strong>of</strong> mixed material to the<br />
contract works, whether batched on-site or <strong>of</strong>f-site,<br />
shall be accompanied by a delivery ticket giving the<br />
following details:<br />
• Delivery ticket number;<br />
• Vehicle registration number;<br />
• Material type <strong>and</strong> mix classification;<br />
• Penetration grade <strong>of</strong> bitumen used; <strong>and</strong><br />
• Quantity.<br />
For material batched <strong>of</strong>f-site, the delivery ticket shall<br />
also give the following details:<br />
• Customer name <strong>and</strong> Delivery site number;<br />
• Source <strong>of</strong> supply;<br />
• Date <strong>and</strong> time loaded; <strong>and</strong><br />
• Date <strong>and</strong> time delivered.<br />
7.8.5 Copies <strong>of</strong> the delivery tickets shall be<br />
passed to the Project Manager for his retention.<br />
7.9 TACK AND BOND COAT<br />
APPLICATION<br />
7.9.1 The type <strong>of</strong> tack or bond coat to be used for<br />
the particular material being laid is as specified in<br />
Clause 3.6.<br />
7.9.2 Tack <strong>and</strong> bond coats shall be applied not<br />
more than 48 h in advance <strong>of</strong> surfacing. The target<br />
rate <strong>of</strong> application shall be in accordance with<br />
BS 594987. Tack <strong>and</strong> bond coat may be applied to<br />
damp surfaces but ponded or st<strong>and</strong>ing water shall<br />
be removed as specified in Clauses 7.5 <strong>and</strong> 7.6.<br />
7.9.3 Tack <strong>and</strong> bond coats shall be applied<br />
uniformly, free <strong>of</strong> streaks <strong>and</strong> blobs in accordance<br />
with BS 434-2 by mobile mechanical tank-spraying<br />
units complying with BS 3136-2. The tack or bond<br />
coat shall be allowed to ‘break’ completely before<br />
laying proceeds. Where the size or shape <strong>of</strong> an<br />
area to be sprayed precludes mobile operation,<br />
pressure spraying equipment or h<strong>and</strong>-spraying<br />
complying in accordance with BS 434-2 will be<br />
permitted with the approval <strong>of</strong> the Project Manager.<br />
July 2010 21