Specification 12 <strong>Hot</strong> <strong>Rolled</strong> <strong>Asphalt</strong> <strong>and</strong> <strong>Macadam</strong> Appendix Z – Guidance Notes on the Preparation<br />
for Airfields <strong>of</strong> Job Specifications<br />
Z.11.2 The choice <strong>of</strong> whether to cover over or<br />
ramp around manholes <strong>and</strong> aviation ground<br />
lighting fixtures will depend upon, respectively:<br />
• the services located in the manhole <strong>and</strong> the<br />
importance <strong>of</strong> maintaining immediate access to<br />
them; <strong>and</strong><br />
• the needs <strong>of</strong> the Aerodrome to maintain all<br />
ground lighting fixtures operational.<br />
Agreement should be sought with the Aerodrome<br />
Authority/Station staff.<br />
Z.11.3 Typical values that can be used in sub-<br />
Clauses 7.23.4 to 7.23.6 subject to agreement<br />
with the Aerodrome Authority/Station staff are as<br />
given in Table Z.5.<br />
Z.12 ROUTINE TESTING<br />
Routine testing <strong>of</strong> designed <strong>Hot</strong> <strong>Rolled</strong> <strong>Asphalt</strong> for<br />
air voids content <strong>and</strong> <strong>of</strong> binder course <strong>Asphalt</strong><br />
<strong>Concrete</strong> (<strong>Macadam</strong>) for percentage refusal<br />
density throughout the construction period may be<br />
omitted for small works only.<br />
Z.13 TEMPERATURE OF SURFACING<br />
In assessing the temperature <strong>of</strong> the freshly laid<br />
surfacing, consideration should be given to the<br />
likelihood <strong>of</strong> the temperature at depth being<br />
TABLE Z.5 TYPICAL VALUES FOR TEMPORARY RAMPS<br />
Distance from runway centre line:<br />
Limit <strong>of</strong> applicability <strong>of</strong> Sub-Clause<br />
Minimum for transverse ramps<br />
Maximum longitudinal gradient<br />
Maximum transverse gradient<br />
Minimum spacing <strong>of</strong> ramps<br />
Min. thickness <strong>of</strong> ramp material<br />
Maximum depth <strong>of</strong> ramp<br />
greater than that at the surface. If the<br />
temperature is required to be taken, a hole should<br />
be drilled 40 mm deep, a measurement device<br />
with suitable accuracy (± 1°C) inserted <strong>and</strong> the<br />
hole filled with glycerine. The temperature should<br />
be determined after the reading has stabilised<br />
whilst at different depths.<br />
Z.14 REGULARITY FOR TAKING CORE<br />
SAMPLES<br />
The regularity for taking cores for monitoring<br />
should be a minimum <strong>of</strong> one every 1000 m². For<br />
small works, the regularity may have to be<br />
increased to obtain sufficient results to make an<br />
assessment on.<br />
Z.15 METEOROLOGICAL DATA<br />
In deciding whether to <strong>of</strong>fer meteorological data<br />
about the site, the ease <strong>of</strong> availability <strong>of</strong> the data<br />
<strong>and</strong> the possible usefulness <strong>of</strong> the data (in terms<br />
<strong>of</strong> the expected season when the work is to be<br />
carried out <strong>and</strong> the size <strong>of</strong> the works) need to be<br />
considered.<br />
Sub-Clause 7.23.4 Sub-Clause 7.23.5 Sub-Clause 7.23.6<br />
22.5 m<br />
10.0 m<br />
1.0 % *<br />
2.0 %<br />
110 m<br />
40 mm<br />
75 mm<br />
22.5 m<br />
†<br />
2.0 % *<br />
2.5 %<br />
†<br />
40 mm<br />
†<br />
July 2010 53<br />
n/a<br />
n/a<br />
2.0 % *<br />
2.5 %<br />
* If the existing longitudinal gradient is at, or close to, the maximum permissible in the st<strong>and</strong>ard criterion<br />
then, depending on the direction <strong>of</strong> working, it may be necessary to obtain dispensation from the<br />
Aerodrome Authority/Station staff to increase this value for temporary ramps.<br />
† Not normally applicable, but otherwise to be agreed with the Aerodrome Authority/Station staff on a job<br />
specific basis.<br />
n/a<br />
n/a<br />
n/a