Specification 12 <strong>Hot</strong> <strong>Rolled</strong> <strong>Asphalt</strong> <strong>and</strong> <strong>Macadam</strong> for Airfields 8 Trials<br />
8 Trials<br />
8.1 GENERAL<br />
Trials shall be carried out on all asphalt mixtures,<br />
other than Pervious <strong>Macadam</strong> drainage material,<br />
proposed for use in the Works. For small works,<br />
the procedures <strong>and</strong> requirements for the preliminary<br />
<strong>and</strong> final trials may be combined <strong>and</strong>/or modified at<br />
the discretion <strong>of</strong> the Project Manager.<br />
8.2 PRELIMINARY TRIALS<br />
8.2.1 For each asphalt, after the design mixture<br />
or recipe mixture has been approved by the Project<br />
Manager (see Clauses 4.2, 4.3 <strong>and</strong> 5.2), the<br />
Contractor shall mix at least one 20 tonne batch <strong>of</strong><br />
the material for laying in preliminary trials. At the<br />
discretion <strong>of</strong> the Project Manager, this requirement<br />
may be modified for regulation or ramping material.<br />
8.2.2 Preliminary trial mixtures, for design or<br />
recipe mixtures, shall be made up in the mixers that<br />
the Contractor proposes to use at the appropriate<br />
mixing temperatures <strong>and</strong> with the aggregates<br />
proportioned from either:<br />
• the various hot bins for a Batch Mixer; or<br />
• the cold feed hoppers for a Continuous Drum<br />
Mixer<br />
to produce the required aggregate grading with the<br />
binder content at the appropriate design binder<br />
content or specified figure for recipe mixtures.<br />
8.2.3 Preliminary trial mixtures for design <strong>Hot</strong><br />
<strong>Rolled</strong> <strong>Asphalt</strong> mixtures shall be made up from the<br />
laboratory design mixtures determined in<br />
accordance with Clause 4.2.<br />
8.2.4 The preliminary trial mixtures shall be laid<br />
on disused pavements within the airfield boundary,<br />
in locations selected by the Project Manager. The<br />
materials shall be laid <strong>and</strong> compacted according to<br />
the requirements <strong>of</strong> BS 594987 <strong>and</strong> this<br />
Specification, according to material type <strong>and</strong><br />
specified thickness.<br />
8.2.5 The mixture shall be transported to the<br />
airfield <strong>and</strong> laid <strong>and</strong> compacted on a clean firm <strong>and</strong><br />
level test area, not being part <strong>of</strong> the works, using<br />
delivery, paving <strong>and</strong> compaction machinery that the<br />
Contractor proposes to use during the works. The<br />
area shall be tack or bond coated prior to laying.<br />
The Contractor shall select paving <strong>and</strong> compaction<br />
operations such that no laying defects such as<br />
dragging or surface blemishes result, to the<br />
satisfaction <strong>of</strong> the Project Manager. The Project<br />
Manager may order further 20 tonne loads to be laid<br />
until a satisfactory result is achieved.<br />
(NOTE 1. Attention needs to be given to the material<br />
feed rate via the paver screws to the screed to avoid<br />
dragging <strong>and</strong> segregation.)<br />
(NOTE 2. For planning purposes, the following equations<br />
will assist the Contractor to select paving <strong>and</strong> rolling rates<br />
to achieve the minimum specified number <strong>of</strong> roller passes<br />
before the surfacing has cooled to the minimum<br />
temperature for compaction:<br />
Rolling length (m) = average paving speed (m/min) x 8 (min)<br />
Roller passes = (Rolling rate/Paving Rate) x No <strong>of</strong> Rollers<br />
where:<br />
Rolling rate (m²/min) = Roller width (m) x Roller speed (m/min)<br />
Paver rate (m²/min) = Paver width (m) x Paver speed (m/min))<br />
8.2.6 The paving <strong>and</strong> rolling rates, demonstrated<br />
to be satisfactory during the laying <strong>of</strong> the trial<br />
mixture, shall be agreed with the Project Manager<br />
<strong>and</strong> shall be adhered to during the main works.<br />
8.2.7 The Contractor shall submit the results <strong>of</strong><br />
an analysis, carried out in accordance with<br />
BS EN 12697-1 <strong>and</strong> BS EN 12697-2, to the Project<br />
Manager for each load <strong>of</strong> the trial mixture laid to<br />
demonstrate compliance with the requirements <strong>of</strong><br />
Clauses 4.4, 4.5 or 5.2.<br />
8.2.8 If the preliminary trials indicate that the trial<br />
mixtures are unsatisfactory for mechanical<br />
spreading <strong>and</strong> compacting, or fail to produce the<br />
specified surface accuracy or result in surface<br />
blemishes which are unacceptable, the proportion<br />
<strong>of</strong> binder <strong>and</strong> the grading <strong>of</strong> the combined<br />
aggregates <strong>and</strong> filler aggregate may be slightly<br />
modified within the limits <strong>of</strong> the Specification.<br />
(NOTE. If changes outside <strong>of</strong> the specification limits are<br />
required, a new design may be necessary for non-recipe<br />
mixtures.)<br />
8.2.9 Further preliminary trials shall then be laid<br />
to demonstrate that a satisfactory mixture has been<br />
achieved. The Project Manager will then agree the<br />
mixture <strong>and</strong> appropriate specification limits <strong>and</strong><br />
authorise the laying <strong>of</strong> a final trial area as described<br />
in Clause 8.3.<br />
32 July 2010