400/220 kV Ranchi Substation<br />
“We all know Rome was not built in a day. So is bay extension at Maithon Substation on turnkey<br />
the case with 400/220 kV Ranchi Substation basis with a stringent completion schedule of 22<br />
which has not been built in a day, neither has it<br />
been built in a week nor in a month. But at L&T,<br />
a green field 400/220 kV Substation could be<br />
built barely in six months” These are the words of<br />
appreciation as quoted by the GM (<strong>Construction</strong>)–<br />
POWERGRID, Patna in his letter dated 15.05.2007<br />
addressed to L&T. Charging a green field 400/220<br />
kV substation within six months from the possession<br />
of the land has indeed set a benchmark to L&T’s<br />
proactive service in meeting the client’s<br />
requirement.<br />
On May 27, 2005, LOA for Rs. 52.18 crore was<br />
issued by POWERGRID for the construction of a<br />
green field 400/220 kV Substation at Ranchi and<br />
months. Though the works for Maithon bay<br />
extension started on schedule, the work for Ranchi<br />
green field project could not be started due to<br />
disputes in possession of land. Ultimately in<br />
<strong>Oct</strong>ober 2006 the land was formally handed over to<br />
L&T for construction. Consequently the project zero<br />
date started with an initial delay of 16 months with<br />
respect to the original L2 schedule.<br />
Immediately after handing over the land,<br />
POWERGRID management requested L&T to<br />
tighten schedule and execute the project as per the<br />
original completion plan. This request which<br />
seemed to be an impossible task, was accepted as a<br />
challenge and plans were charted with the<br />
400 kV air insulated substation at Ranchi for POWERGRID