25.04.2013 Views

Oct - Dec 2009 • Vol. No. 32 Issue No. 2 • - L&T Construction

Oct - Dec 2009 • Vol. No. 32 Issue No. 2 • - L&T Construction

Oct - Dec 2009 • Vol. No. 32 Issue No. 2 • - L&T Construction

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

400/220 kV Ranchi Substation<br />

“We all know Rome was not built in a day. So is bay extension at Maithon Substation on turnkey<br />

the case with 400/220 kV Ranchi Substation basis with a stringent completion schedule of 22<br />

which has not been built in a day, neither has it<br />

been built in a week nor in a month. But at L&T,<br />

a green field 400/220 kV Substation could be<br />

built barely in six months” These are the words of<br />

appreciation as quoted by the GM (<strong>Construction</strong>)–<br />

POWERGRID, Patna in his letter dated 15.05.2007<br />

addressed to L&T. Charging a green field 400/220<br />

kV substation within six months from the possession<br />

of the land has indeed set a benchmark to L&T’s<br />

proactive service in meeting the client’s<br />

requirement.<br />

On May 27, 2005, LOA for Rs. 52.18 crore was<br />

issued by POWERGRID for the construction of a<br />

green field 400/220 kV Substation at Ranchi and<br />

months. Though the works for Maithon bay<br />

extension started on schedule, the work for Ranchi<br />

green field project could not be started due to<br />

disputes in possession of land. Ultimately in<br />

<strong>Oct</strong>ober 2006 the land was formally handed over to<br />

L&T for construction. Consequently the project zero<br />

date started with an initial delay of 16 months with<br />

respect to the original L2 schedule.<br />

Immediately after handing over the land,<br />

POWERGRID management requested L&T to<br />

tighten schedule and execute the project as per the<br />

original completion plan. This request which<br />

seemed to be an impossible task, was accepted as a<br />

challenge and plans were charted with the<br />

400 kV air insulated substation at Ranchi for POWERGRID

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!