Two different views of the substation<br />
6 CVTs, 14 sets of isolators and 12 LA. Unloading,<br />
erection, testing and commissioning of owners<br />
supply materials like two 80 MVA shunt reactor was<br />
also included in the scope along with all associated<br />
civil works.<br />
The complete scope of <strong>32</strong> Bays ( 21 <strong>No</strong>s 400 kV Bays,<br />
10 <strong>No</strong>s 220 kV Bays & 1 <strong>No</strong> 66 kV Bay) at Ranchi<br />
substation was completed in record time by<br />
mobilizing the resources as required for crashing the<br />
project completion schedule. Also, the close<br />
coordination with the engineering team and vendors<br />
ensured the sequential release of drawings / delivery<br />
of materials which ultimately squeezed the<br />
completion schedule since the work was taken up in<br />
almost all fronts simultaneously.<br />
Safety and quality was given topmost priority<br />
and the project was completed with zero<br />
accident. A labour colony was also constructed<br />
with all basic amenities, good hygiene and<br />
medical care in order to retain and motivate<br />
the work force.<br />
T.A.Rao<br />
Sector Project Manager<br />