dedicated execution / co-ordination team of L&T two 315 kVA auto transformer and one 80 MVA<br />
and POWERGRID. The two teams together left no bus reactor was also included in the scope.<br />
stone unturned and began the works in two shifts<br />
with 800 workmen bustling with activity to give<br />
shape to their plans and blue prints.<br />
This apart, the scope also included engineering,<br />
supply, erection & commissioning of CRP alongwith<br />
complete sub-station automation system with remote<br />
The civil scope of works involved 52000 cu.m of access from Jamshedpur / Kolkata. All other auxiliary<br />
excavation, 11835 cu.m of RCC for equipment / services such as illumination and fire fighting were<br />
tower foundations, complete structure & finishes also included in the package.<br />
for control room building, 1.4 km cable trench,<br />
2.6 km bitumen road and 862 t of GI structures.<br />
In addition to the main contract, LOA for Rs. 15.33<br />
crore was issued on 16 February 2006 by<br />
Erection, testing and commissioning scope POWERGRID for 400 kV bay extensions in Ranchi<br />
includes major equipment for 400 kV Substation with a completion schedule of 18<br />
requirements like 8 circuit breakers, 24 CTs, 12 months from the date of LOA. Work for this package<br />
CVTs, 22 sets of isolators and 15 LA. Major was also taken up simultaneously along with the<br />
equipment for 220 kV requirement like 8 circuit main package.<br />
breakers, 24 CTs, 18 CVTs, 29 sets of Isolators<br />
and 18 LA. Unloading, erection, testing and<br />
commissioning of owners supply materials like<br />
Scope for Ranchi (extension) package includes 400<br />
kV major equipment like 4 circuit breakers, 12 CTs,<br />
Control room as a part of the substation project