FY 2001 / 2002 FY 2002 / 2003<br />
Disposed (at solid waste 25,150 Metric tons 17,310 Metric tons<br />
facility)<br />
Disposed (elsewhere) 6,668 Metric tons 6,380 Metric tons<br />
Subtotal 31,818 Metric tons 23,690 Metric tons (26% <strong>reduction</strong>)<br />
Recycled (at solid waste 996 Metric tons 3003 Metric tons<br />
facility)<br />
Recycled (elsewhere) 0 tons 6,034 Metric tons<br />
Subtotal 996 Metric tons 9037 Metric tons (9-fold increase)<br />
(SOURCE: http://www.recyclecddebris.com/rCDd/Handbook, VISITED ON 10/08/2009)<br />
d. Port of Oakland<br />
The Youth Employment Partnership to dismantle the Port of Oakland’s Building 733. The<br />
large warehouse yielded 136,800 board meters of mainly old-growth Douglas fir.<br />
The total expense to deconstruct- $330,000<br />
Income from salvaged lumber-$280,000<br />
Net cost was $50,000.<br />
Demolition bid: $150,000. (Urban Ecologist, Number 2, 1997).<br />
(SOURCE:http://www.crra.com/rrarc/publications/Deconstruction.pdf, VISITED ON 10/11/2009)<br />
e. San Francisco’s Presidio<br />
Beyond <strong>Waste</strong> and San Francisco Community Recyclers deconstructed Building 901 at San<br />
Francisco’s Presidio. The structure came down in one month, yielding 20,117 board meter of<br />
old growth Douglas fir and Port Orford cedar for salvage.<br />
Total deconstructing expense (including labor, equipment, and administrative costs), was<br />
$53,000.<br />
Income from the salvaged wood - $43,660<br />
Net cost of deconstruction-$9,340<br />
Demolition bid - $16,800<br />
(SOURCE:http://www.crra.com/rrarc/publications/Deconstruction.pdf, VISITED ON 10/11/2009)<br />
147