GETCO/E/TS – XMER01power/R4 Sept <strong>08</strong><br />
1.30.5 TYPE TESTS ON BOUGHT OUT ITEMS:<br />
1. Bushing (Type test as per IS:2099/IEC:137)<br />
2. OLTC (Temp Rise of c<strong>on</strong>tact, Short circuit current test, Mechanical test &<br />
Dielectric test as per IEC:214 and IP:55 test <strong>on</strong> driving mechanism box)<br />
3. Buchholz relay (as per IS:3637) & IP-55 <strong>on</strong> terminal box<br />
4. Air cell (Flexible air separator) – Oil side coating, Air side under coating, Air side<br />
outer coating and coated fabric as per IS:3400/BS:903/IS:7016.<br />
5. Oil pump – vacuum test, oil pressure test at 1 kg/cm2 for 24 hrs., Temperature<br />
rise test by resistance method, IP-55 for terminal box.<br />
6. Cooling fan and motor assembly – Free air delivery, Temperature rise, sound<br />
level, running at reduced voltage, IP-55 for terminal box.<br />
7. MOG & terminal box for IP-55 degree of protecti<strong>on</strong><br />
1.31 TESTS ON OLTC:<br />
1.31.1 The various tests (routine and type) as stipulated in the IEC Publicati<strong>on</strong> No. 214-<br />
19<str<strong>on</strong>g>66</str<strong>on</strong>g> (as amended up to-date) shall be carried out.<br />
1.31.2 Type test certificate copies of oscillograms as called for in IEC publicati<strong>on</strong> 214 shall<br />
be furnished by the supplier.<br />
1.32 TEST REPORTS:<br />
1.32.1 After all the tests have been completed 3 copies of each test report shall be furnished<br />
to the GETCO for his approval prior to the dispatch of equipment. Soft copy of<br />
test reports for tests results obtained from software shall be<br />
submitted for approval and record.<br />
1.32.2 All the reports of inspecti<strong>on</strong>s like stage, acceptance, routine & type tests<br />
carried out <strong>on</strong> each transformer including test certificates for bought out<br />
items, in bound volume, shall be submitted before dispatch. Also <strong>on</strong>e copy<br />
shall be sent al<strong>on</strong>g with transformer.<br />
1.33 FURTHER TESTS:<br />
The GETCO reserves the right of having any other reas<strong>on</strong>able test carried out at his<br />
own expense to ensure that the transformer compiled with requirements of this<br />
specificati<strong>on</strong>.<br />
1.34 LOSS/DAMAGES:<br />
1.34.1 The Purchaser shall not be resp<strong>on</strong>sible for any damage to the equipment during<br />
commissi<strong>on</strong>ing if such damage results from faulty or inadequate acti<strong>on</strong>.<br />
1.34.2 Seller shall not be liable for any loss, damage or injury to property or pers<strong>on</strong>s at the<br />
installati<strong>on</strong> site unless such damages or injuries are caused by any and or<br />
negligence of the supervising erector.<br />
1.35 TECHNICAL AND GUARANTEED PARTICULARS:<br />
The bidder shall furnish all guaranteed technical particulars as called for in, Secti<strong>on</strong> –<br />
III, Schedule – A of this specificati<strong>on</strong>. Particulars, which are subject to guarantee,<br />
Sign and Seal of Bidder Page 35 of 87