GETCO/E/TS – XMER01power/R4 Sept <strong>08</strong><br />

Wc= Copper losses in KW; Wp = Auxiliary loss in KW.<br />

1.39 PENALTY FOR HIGHER LOSSES:<br />

In case of order if the figures of losses measured during tests or in service are found<br />

to be higher than the figures guaranteed at the opti<strong>on</strong> of the GETCO will be rejected<br />

or accepted with the reducti<strong>on</strong> in price as under<br />

1.40 REJECTION:<br />

For Ir<strong>on</strong> loss = Rs. 1,60,000/- per KW<br />

For Copper loss = Rs. 70,000/- per KW<br />

For Auxiliary loss = Rs. 60,000/- per kW<br />

1.40.1 The Purchaser may reject transformer, if any of the following c<strong>on</strong>diti<strong>on</strong>s during or<br />

service arises:<br />

i) No load losses or load losses exceed the guaranteed value.<br />

ii) Impedance value exceeds the guaranteed value by + 10% or more.<br />

iii) Oil or winding temperature rise exceeds the specified value by 5 deg. C.<br />

iv) Transformer fails <strong>on</strong> impulse test.<br />

v) Transformer fails <strong>on</strong> power frequency voltage withstand test.<br />

vi) The difference is impedance values of any two phase during single phase short<br />

circuit impedance test exceeds 2% of the average value guaranteed by the<br />

manufacturer / c<strong>on</strong>tractor.<br />

vii) Transformer is proved to have been manufactured not in accordance with<br />

agreed specificati<strong>on</strong>.<br />

1.40.2 The Purchaser reserves the right to retain the rejected transformer and use it until<br />

the bidder replaces the defective transformer by a new transformer, within a<br />

reas<strong>on</strong>able period, at no extra cost to the GETCO. In such case the transportati<strong>on</strong>,<br />

loading, unloading <strong>on</strong> plinth, inspecti<strong>on</strong>, erecti<strong>on</strong>, testing & commissi<strong>on</strong>ing charges<br />

shall be bourn by the bidder.<br />

1.41 TRAINING TO ENGINEERS:<br />

1.41.1 The successful bidder will be required to grant facilities for training to minimum two<br />

Engineers to be nominated by the GETCO, at bidders’ works particularly in the<br />

manufacture, assembly, operati<strong>on</strong> and maintenance of transformer. The bidder<br />

should please state the general c<strong>on</strong>diti<strong>on</strong> of training and number of Engineers and<br />

durati<strong>on</strong> of training for whom such training will be arranged by him.<br />

1.41.2 Bidder shall at his cost arrange for the above training facilities and in additi<strong>on</strong> shall<br />

bear all living expenses. The Purchaser shall <strong>on</strong>ly pay to and fro passage of the<br />

trainees. Bidder shall indicate following in the prices schedule.<br />

a) The lump sum amount of training for the above training facilities.<br />

b) Price reducti<strong>on</strong> / additi<strong>on</strong> for number of trainees specified herein.<br />

1.42 Guarantee period will be reck<strong>on</strong>ed from the date of receipt of 100 % accessories<br />

and not from the date of receipt of main tank <strong>on</strong>ly.<br />

Sign and Seal of Bidder Page 37 of 87