DWDU, Rajkot<br />

Table No, 41.iii: Technical Details <strong>of</strong> Bio-gas<br />

Detailed Cost Estimate for a 3 Cum Capacity Bio-gas<br />

S<br />

No Particulars Unit No L W H/D Qty Rate Amount<br />

1 Excavation <strong>of</strong> pit for main Tank ( Digester) Cum 1 22/7X2X2X1.5 18.84<br />

i Extra Excavation for round shape <strong>of</strong> Digester Tank Cum 1 4/3X22/7X2X2X.5 8.37<br />

ii Excavation <strong>of</strong> foundation for Fedder Tank Cum 1 22/7X0.8X0.8X0.5 1.00<br />

iii Excavation <strong>of</strong> foundation for slurry Tank Cum 1 2.5 1.5 0.5 1.88<br />

30.09 41 1233.82<br />

2 PCC in 1:2:4 cement Concrete<br />

i In bottom <strong>of</strong> the main Digester Tank 3" thick Cum 1 22/7X2X2X0.075 1.88<br />

ii In bottom <strong>of</strong> the Feeder Tank 3" thick Cum 1 22/7X0.8X0.8X0.075 0.15<br />

iii In bottom <strong>of</strong> the slurry tank 3" thick Cum 1 2.5 1.5 0.075 0.28<br />

2.32 2420 5604.65<br />

3 Brick Work in 1:5 cement mortar<br />

i for construction <strong>of</strong> digester tank dom Cum 1 0.63<br />

ii for construction <strong>of</strong> feeder tank Cum 1 0.20<br />

iii for construction <strong>of</strong> slurry tank Cum 1 0.88<br />

4 Plastering <strong>of</strong> the surface in 1:4 cement mortar 1.71 2280 3896.43<br />

i Digester from Inside and outside Sqm 1 3/2X22/7X1X1 4.71<br />

ii Feeder tank from inside and out side Sqm 1 5.02<br />

iii Slurry tank from inside and outside Sqm 1 17.6<br />

27.33 74 2022.72<br />

Fixing <strong>of</strong> GI pipe nipple 1" dia and 20cm long on top <strong>of</strong><br />

5 digester dome Job 1 1 150 150<br />

6<br />

Providing <strong>of</strong> gas burner+ HDPE pipe 1/4" +1/2" gate<br />

valve+Hose Nipple, Hose Clamp unit 1 1 1860 1860<br />

Total Constructional Cost in Rs. 14767.61<br />

Detailed Project Report: <strong>IWMP</strong>-III 96