DEVELOPERS’ PROCEDURES<br />
CHAPTER TWO<br />
23. Proposed layout of force main including profiles, type of pipe,<br />
discharge point design <strong>and</strong> air release valve locations.<br />
24. Design of the storm water drainage plan.<br />
25. Any other information considered by either the <strong>developer</strong> or the<br />
<strong>Authority</strong> to be pertinent to the review of the plan.<br />
26. Catalogs, cuts, diagrams, performance curves, <strong>and</strong> charts published<br />
by manufacturers <strong>and</strong> complete electrical components for all<br />
equipment shall be provided.<br />
27. Any project which has water <strong>and</strong>/or sewer service immediately<br />
adjacent to the site shall provide the following in addition to those<br />
outlined above as applicable.<br />
a. Site plan showing location of all proposed <strong>and</strong> existing<br />
utility lines.<br />
b. Layout of streets, parking lots, etc.<br />
c. Floor plan showing designated use of all areas.<br />
d. Internal plumbing plan including fire protection system <strong>and</strong><br />
water meter size.<br />
28. <strong>Water</strong> <strong>and</strong> Wastewater transmission <strong>and</strong> distribution mains shall be<br />
designed for installation within an existing or proposed public<br />
right-of-way. <strong>Gr<strong>and</strong></strong> <strong>Str<strong>and</strong></strong> <strong>Water</strong> <strong>and</strong> <strong>Sewer</strong> <strong>Authority</strong> may at its<br />
discretion grant specific exceptions. The granting of an exception<br />
may be contingent upon the <strong>developer</strong>s compliance with additional<br />
easement, material, <strong>and</strong> design requirements.<br />
29. <strong>Water</strong> systems shall be designed so as to provide fire flow<br />
protection as outlined in the <strong>Gr<strong>and</strong></strong> <strong>Str<strong>and</strong></strong> <strong>Water</strong> <strong>and</strong> <strong>Sewer</strong><br />
<strong>Authority</strong> <strong>Water</strong> System St<strong>and</strong>ards <strong>and</strong> Specifications.<br />
2.4 SUBMISSION OF PROJECT RELATED DOCUMENTS<br />
2.4.1 REQUIRED CERTIFICATION AND/OR PERMITS<br />
The following certificates <strong>and</strong>/or permits/applications shall be provided by<br />
the <strong>developer</strong> prior to approval to construct by the <strong>Authority</strong>.<br />
1. Two (2) copies of completed State Department of Transportation<br />
encroachment permit applications.<br />
Developers’ Procedures July 2009 <strong>Gr<strong>and</strong></strong> <strong>Str<strong>and</strong></strong> <strong>Water</strong> <strong>and</strong> <strong>Sewer</strong> <strong>Authority</strong><br />
Page 10<br />
Developer Policy Manual