SERVICE AUTHORIZATION AND FINAL ACCEPTANCE<br />

CHAPTER FOUR<br />

4.2 MAINTENANCE BOND<br />

In the event a <strong>developer</strong> wishes to obtain service authorization from the <strong>Authority</strong><br />

for the project prior to the completion of all punch list items noted by the<br />

<strong>Authority</strong> during the final inspection <strong>and</strong>/or if paving, ditching, installation or<br />

other utilities or any other activities which may harm the water <strong>and</strong>/or sewer<br />

systems remain, a maintenance bond shall be posted until such time as the punch<br />

list <strong>and</strong>/or other construction activities have been satisfactorily completed <strong>and</strong><br />

approved by the <strong>Authority</strong>. The maintenance bond can be either certified check,<br />

cash or by letter of credit from an acceptable financial institution, <strong>and</strong> shall be for<br />

ten (10%) per cent or as deemed necessary by the <strong>Authority</strong> of the certified cost<br />

of the water <strong>and</strong>/or sewer system constructed for the project as certified by the<br />

project engineer.<br />

The maintenance bond must remain in effect until all punch list items, all other<br />

construction, <strong>and</strong> the revised as-builts are completed, if necessary, <strong>and</strong> approved<br />

by the <strong>Authority</strong>.<br />

4.2.1 FOLLOW-UP INSPECTION<br />

The project engineer shall be responsible for coordinating a follow up<br />

inspection with the project inspector to be attended by the project<br />

engineer, contractor, <strong>Authority</strong> inspector <strong>and</strong> <strong>Authority</strong> operations<br />

personnel. Upon completion of the inspection, the <strong>Authority</strong>'s inspector<br />

will determine if all punch list <strong>and</strong>/or other work has been satisfactorily<br />

completed. Should the project inspector approve the release of the<br />

maintenance bond, he will authorize the New Services Department to<br />

proceed with the release of the maintenance bond without interest.<br />

In the event that punch list items are not completed within a reasonable<br />

time after a project has been approved for operation, or if the <strong>developer</strong><br />

has failed to renew the letter of credit as requested by the <strong>Authority</strong>, the<br />

<strong>developer</strong> will be notified via mail at least five (5) working days, giving<br />

notice that the process to exercise the bond in order to complete the punch<br />

list is to commence. Failure by the <strong>developer</strong> to complete a project punch<br />

list in a reasonable time may jeopardize service requests within the<br />

development until the punch list is completed.<br />

4.3 SERVICE AUTHORIZATION<br />

Service authorization can be issued by the New Services Department upon receipt<br />

of all required documents from the engineer, contractor, <strong>developer</strong>, <strong>and</strong> agencies<br />

as set forth below for the water <strong>and</strong>/or sewer systems constructed. All<br />

documentation should be submitted to the attention of the New Services<br />

<strong>Gr<strong>and</strong></strong> <strong>Str<strong>and</strong></strong> <strong>Water</strong> <strong>and</strong> <strong>Sewer</strong> <strong>Authority</strong> July 2009 Service Authorization <strong>and</strong> Final Acceptance<br />

Developer Policy Manual Page 33