Environmental performance<br />

Environmental performance<br />

Ernest Henry Mining<br />

Megan Moar – Environmental Field Technician, conducts surface water monitoring at Ernest Henry Mining<br />

Environmental challenges<br />

The key environmental challenges at Ernest<br />

Henry Mining (EHM) include:<br />

■■<br />

■■<br />

■■<br />

■■<br />

■■<br />

■■<br />

■■<br />

maximising the efficient use of water<br />

improving stormwater management<br />

during high rainfall events<br />

modelling groundwater drawdown and<br />

recharge (post-closure)<br />

developing sustainable capping strategies<br />

for the tailings dam and waste rock<br />

dumps<br />

updating the Mine Closure Plan<br />

reducing EHM’s financial liability<br />

improving biodiversity and land use<br />

planning.<br />

Environmental protection<br />

expenditures<br />

In 2010 Ernest Henry Mining invested<br />

$2.9 million on environmental protection,<br />

management and initiatives.<br />

Managing environmental risks<br />

EHM continues to maintain its area specific<br />

environmental Aspects and Impacts<br />

Registers. These registers are used to monitor<br />

controls that are implemented to minimise<br />

environmental risks. They also identify where<br />

additional controls can be implemented to<br />

further reduce environmental risk at the mine.<br />

The main risks and controls identified in<br />

these registers are integrated into the budget<br />

planning process.<br />

Continuous environmental<br />

improvement<br />

In 2010, EHM continued to manage<br />

an Environmental Improvement Plan<br />

(EIP), which listed key environmental<br />

improvement initiatives developed from<br />

the Aspects and Impact Registers. An EIP is<br />

developed annually to encourage continual<br />

environmental improvement at our operation.<br />

Our main focus during the year was further<br />

improving water use efficiency and the<br />

management of stormwater on site.<br />

Environmental protection expenditures<br />

and investments by type – EHM<br />

Expenditure/investment<br />

category 2010<br />

Capital $19,800<br />

Environmental<br />

consultants/contractors<br />

Environmental personnel –<br />

employees<br />

$419,498<br />

$660,062<br />

Licences/liability insurance $287,762<br />

Rehabilitation and<br />

decommissioning costs<br />

$432,847<br />

Research and development $185,350<br />

Treatment and disposal of<br />

waste<br />

Monitoring and analysis<br />

equipment<br />

$396,566<br />

$93,084<br />

Operating costs $449,308<br />

Total $2,944,277<br />