<strong>SUNY</strong> <strong>Cobleskill</strong> Facilities Master Plan – Phase 5 Report<br />

November 2011<br />

Approach to Library, Collaboration, and Food Service<br />

While the final FMP does not recommend an addition to the Library, it<br />

does provide more space for the Library by relocating C.A.S.E. and the<br />

Writing Center from the lower floor of Van Wagenen to Alumni Hall. The<br />

FMP envisions the library as a knowledge and media resource as well as a<br />

social hub (secondary to the Student & Community Center). Libraries are<br />

changing and evolving into multi-media environments, with an increasing<br />

focus on digital resources as opposed to print resources. Renovations to<br />

the Van Wagenen Library at <strong>SUNY</strong> <strong>Cobleskill</strong> are proposed for the second<br />

half of this planning cycle. Program and pedagogical change will be<br />

initiated as part of a future renovation. In addition to a renovation of the<br />

building, the final FMP proposes to upgrade the landscape and plaza<br />

area in the immediate vicinity of the Library.<br />

The primary dining facilities on the campus are currently located in<br />

Champlin Hall and Prentice Hall. While the College provided positive<br />

feedback on existing campus Food Service, the FMP relocates one of the<br />

large dining facilities and provides a new “food court,” style dining hall<br />

in the Student & Community Center. In addition, three satellite cafes are<br />

provided across the campus—in Warner-Holmes, Van Wagenen Library,<br />

and the new Center for Agriculture and Natural Resources [CANR]. Other<br />

campus zones, such as the Upper Quad, will be provided with vending<br />

machines and lounge seating.<br />

To address campus Food Service, the final FMP recommends:<br />

•<br />

•<br />

•<br />

•<br />

•<br />

Demolishing Champlin Hall and providing a new food courtstyle<br />

dining hall (275 seats) in the Student & Community Center<br />

Locating the main dining hall (400 seats) in Prentice Hall with<br />

“all-you-care-to-eat” service<br />

Providing a new intimate dining room (75 seats) in Prentice Hall<br />

with higher-quality finishes that is also the American Heritage<br />

dining room / class lab<br />

Maintain the commissary in Prentice Hall<br />

Relocate the main CAS offices to Prentice Hall<br />

Collaboration space is notably lacking on the <strong>SUNY</strong> <strong>Cobleskill</strong> campus.<br />

This type of space includes areas for informal study and conversation that<br />

are more dynamic than typical study rooms. They may accommodate<br />

a range of collaborative learning, from casual to semi-formal, and are<br />

sometimes supported by technology. The FMP proposes to add a significant<br />

number of Collaboration hubs throughout the campus, particularly in<br />

academic buildings and the Student & Community Center.<br />

Approach to Campus Entry Sequence<br />

The sequence of entry from Route 7 is an important consideration not<br />

only for functionality but also for the visual impression created by the<br />

campus. Currently the campus turns its “back side” to Route 7, with the<br />

“front door” of Knapp Hall facing the interior of the campus. The final<br />

FMP addresses the challenge of the entry sequence and presence of the<br />

campus along Route 7 in several ways:<br />

•<br />

•<br />

•<br />

The Student & Community Center faces Route 7 and is accessible<br />

from the highway, creating a prominent “front door” to the<br />

campus<br />

A new traffic roundabout with landscaping and collegiate signage<br />

is proposed at the main campus entrance<br />

A tree buffer is provided along Route 7, creating an attractive<br />

entry sequence, shielding the campus from the highway and<br />

drawing attention to the new Student & Community Center<br />

Approach to Albany Avenue<br />

Albany Avenue is the loop road that encircles the east side of the campus.<br />

The FMP proposes several changes to Albany Avenue to improve vehicular<br />

access and pedestrian safety:<br />

•<br />

•<br />

•<br />

Reconstruct paving and curbs<br />

Repair parking surfaces along Albany Avenue<br />

Reconfigure portions of the road to provide cul-de-sacs at the<br />

new Student & Community Center and Prentice Hall<br />

Approach to Parking<br />

As mentioned previously, the campus does not have a critical need for<br />

additional parking spaces. There is, however, a need to upgrade or<br />

repair the surface of several lots and to relocate some parking spaces for<br />

better functionality. The FMP proposes minor changes to campus parking,<br />

including:<br />

•<br />

•<br />

•<br />

•<br />

Relocate the lot adjacent to the Arena Center to make room for<br />

the new covered Arena<br />

Provide a new parking lot across the road from the Arena Center<br />

to accommodate trailers and RVs during events<br />

Expand the F-Lot with additional parking spaces<br />

Repair and upgrade existing parking lots campus-wide including<br />

lighting, curbs, paving, drainage, and signage<br />

Capital Funding<br />

Over the course of the FMP process, recommendations that further the<br />

mission and vision of the College have been the focus. The proposed<br />

initiatives are allocated to three timeframes, the five-year periods of 2013-<br />

2018, 2018-2023, and 2023-2029. The distribution of projects between<br />

these timeframes is based on campus input, phasing sequences, and<br />

estimated project timelines. Costs are assigned to each funding cycle:<br />

Funding Cycles Project Cost Escalated Cost<br />

2013-2018 $63,091,155 $110,209,489<br />

2018-2023 $88,347,249 $185,517,150<br />

2023-2029 $5,666,500 $14,303,636<br />

Total $157,104,904 $310,030,275<br />

Lead-in initiatives, which have already commenced or are projected to<br />

begin prior to 2013, are included in the project phasing but will not<br />

impact plans for new capital funding. These initiatives include:<br />

•<br />

•<br />

•<br />

•<br />

•<br />

Wheeler Hall Addition and Renovation<br />

2011 Facilities Master Plan [FMP]<br />

Campus-wide Academic Study<br />

Knapp Plaza<br />

Center for Agriculture & Natural Sciences [CANR]<br />

10