KRECOMMENDATIONS<br />

<strong>SUNY</strong> <strong>Cobleskill</strong> Facilities Master Plan – Phase 5 Report<br />

November 2011<br />

4M IMPROVE OPEN SPACE QUALITY BY PROVIDING NEW LIBRARY<br />

PLAZA<br />

4O IMPROVE OPEN SPACE QUALITY AND ACCESSIBILITY BY CREATING<br />

LANDSCAPED COLLEGE YARD<br />

4R PROVIDE ADDITIONAL GRAZING AND CROP LAND<br />

Graphic K40<br />

Library Plaza<br />

(at left)<br />

Graphic K41<br />

College Yard (at center)<br />

This initiative provides an allowance for the acquisition of approximately<br />

200-acres to support the School of Agriculture & Natural Resources. It is<br />

expected that the majority of this land will be for the production of livestock<br />

feed. Some of this need, however, is for additional pasture land in order for<br />

the College to meet confined animal feed operation [CAFO] guidelines.<br />

Such additional pasture acreage does not need to be contiguous and<br />

the College will support animal transport to non-contiguous locations.<br />

While the FMP only provided an allowance for 200-acres at the College’s<br />

request, the need is far in excess and the College could realistically utilize<br />

over 450-acres of additional land should funding become available.<br />

4S RECONSTRUCT PARKING LOT AT NEW EQUINE ARENA<br />

The final FMP proposes a new landscaped plaza adjacent to Van Wagenen<br />

Library. This initiative includes:<br />

•<br />

•<br />

•<br />

New plaza with walkways and ADA ramps<br />

Street furniture and lighting<br />

Plantings<br />

This initiative provides a landscaped open space at the south end of the<br />

campus, between the new Student & Community Center and the F-Lot. The<br />

new College Yard will include paved walkways, plantings, and lighting,<br />

and will serve as an open space for the nearby dormitories. It will also<br />

create an attractive entrance to the Student & Community Center from the<br />

F-Lot parking area.<br />

The final FMP proposes a new Equestrian Arena to be located on the site<br />

of an existing parking lot (1I); this initiative provides a replacement for the<br />

existing parking lot.<br />

4T CONSTRUCT NEW PARKING LOT AT UPPER EQUINE FACILITY<br />

This initiative provides a new parking lot for trailers and RVs at the upper<br />

equine facility, adjacent to the existing Horse Stalls (Hangar Building).<br />

4N RECONSTRUCT SERVICE COMPLEX PARKING AND IMPROVE<br />

ADJACENT OPEN SPACE<br />

The aim of this initiative is to improve the parking lot, paving, and open<br />

spaces adjacent to the Mackey Service Complex.<br />

4P UPGRADE EXISTING WALKWAYS CAMPUS-WIDE<br />

This initiative provides an allowance for the demolition and replacement<br />

of sidewalks campus-wide to improve pedestrian circulation and ADA<br />

accessibility. Lighting and minor plantings are also included.<br />

4U PROVIDE STAIRWAY AND PEDESTRIAN CONNECTION FROM<br />

BOUCK HALL TO NEW FIELDHOUSE<br />

This initiative provides a new staircase between Bouck Hall and the<br />

Fieldhouse.<br />

4Q PROVIDE TREE BUFFER ALONG ROUTE 7<br />

This initiative provides an allowance to plant trees along the east side of<br />

Route 7.<br />

4V UPGRADE PARKING LOTS CAMPUS-WIDE<br />

This initiative provides an allowance to replace and repair existing parking<br />

lots throughout the campus.<br />

66