<strong>EBN</strong> <strong>Notional</strong> <strong>Field</strong> <strong>Development</strong> Plan<br />
4.2.2 National Coordination Regulation<br />
In 2010, the NCR for state, provinces, and municipalities came into force under the (new) Spatial<br />
Planning Act (SPA) (ref. par. 3.5.2., in particular 3.6.3, SPA). Further detail is available in paragraph 9a of<br />
the Mining Act (MA).<br />
The regulation aims to make the decision making process for (changes to) spatial plans and associated<br />
permitting procedures, faster and more efficient. The targeted efficiency improvement also proposes a<br />
preference for one governmental organization to become the responsible authority in the decision<br />
making process.<br />
Exploration and production (E&P) infrastructure projects have become subject to the regulation, as they<br />
concern large energy projects of national interest, that need to be incorporated into spatial plans.<br />
Article 141a of the MA declares this procedure applicable to mining activities (i.e. mining works): a) used<br />
in the exploration or production phase within or under certain nature conservation areas, b) for the<br />
storage of substances, and c) for pipelines (primarily or largely) related to the transport of natural<br />
resources resulting from the exploration or production thereof.<br />
This NCR is meant to shorten and streamline the time span of the large diversity of permit procedures<br />
involved in large-scale energy and infrastructure projects. The urban planning decision will take place on<br />
a central level, as does the coordination of the permits. By coordinating the preparation and handling of<br />
the permit procedures simultaneously, a better cooperation between authorities is realized and all<br />
relevant information can be considered in the decision making process. This coordination is linked to the<br />
Ministry Zoning Plan (MZP).<br />
Summarising, the NCR contains:<br />
• Notification of the project should be made to the Minister of Economic Affairs, Agriculture,<br />
and Innovation;<br />
• The Ministers of Economic Affairs, Agriculture, and Innovation and Infrastructure and<br />
Environment should determine a National Integration Plan (NIP) which is procedure for<br />
zoning at national level for spatial anchoring of the initiative<br />
• The procedures and required approvals for this integration plan are specific and require the<br />
Ministry of Economic Affairs, Agriculture and Innovation to render a decision on the<br />
application within +/- 6 months.;<br />
• Once an appeal at the Division of the Council of State (Department) has been filed, the<br />
Department is required to rule within six months after the appeal period (Article 1.6 Crisis<br />
and Recovery Law).<br />
© 2011 Halliburton All Rights Reserved<br />
127