d. Increased permit fees are applicable only to the Portage/Catawba<br />

Isl<strong>and</strong> Sewer Sub-District. Increased permit fees are charged on a per<br />

month <strong>and</strong> prorated basis based on those properties:<br />

(1) that were originally assessed <strong>for</strong> developed property within the<br />

PCI-Sewer Sub-District; <strong>and</strong>,<br />

(2) that were served an Order to connect to the public <strong>sewer</strong> system<br />

within 120 days of the Order; <strong>and</strong>,<br />

(3) that were granted a sixty (60) day extension; <strong>and</strong>,<br />

(4) that have not, as of the end of the combined 180 day connection<br />

period, connected to the public sanitary <strong>sewer</strong>.<br />

3.10.2 Inspection Fees <strong>for</strong> All Sewer Sub-Districts:<br />

a. INSPECTION FEE: $100.00<br />

b. PLAN REVIEW/INSEPCTION FEE DEPOSIT: $750.00<br />

Explanation of (Plan Review) Inspection Fees:<br />

a. An inspection fee shall be charged <strong>for</strong> each new building <strong>sewer</strong> being<br />

connected to the public sanitary <strong>sewer</strong> or appurtenance.<br />

b. When new sanitary <strong>sewer</strong> mains (public or private) are installed or<br />

extended into new subdivisions, developments, or other special projects<br />

by private developers, the developer shall reimburse the Department <strong>for</strong><br />

all plan review <strong>and</strong> inspection costs incurred by the Department on the<br />

project. A plan review/inspection fee deposit shall be required from the<br />

developer at the time of application <strong>for</strong> permit. When final construction<br />

approval has been granted by the Department’s inspector, all<br />

Department plan review <strong>and</strong> inspection costs shall be calculated by the<br />

Department. The Department shall include one (1) hour of inspection<br />

time in the cost <strong>for</strong> the final visual inspection of the sanitary <strong>sewer</strong><br />

improvements to be made after one (1) year of operation (warranty<br />

period). Any overrun in plan review/inspection costs over the original<br />

amount deposited shall be billed to <strong>and</strong> paid by the developer. Thirty<br />

(30) days shall be given to remit payment from the developer. If total<br />

plan review/inspection costs are less than the original amount<br />

deposited, the Department shall refund the difference to the developer<br />

as soon as reasonably possible after final construction approval.<br />

3.10.3 Contractor's License Fee:<br />

Yearly License Fee:<br />

$ 50.00 (see Section 3.8.0 <strong>for</strong> requirements)<br />

3.10.4 Processing Fee (when certifying delinquent <strong>sewer</strong> charges):<br />

Charge per account: $ 50.00<br />

3.10.5 Connection Charge <strong>for</strong> Danbury Township Sewer Sub-District #7 only:<br />

Danbury Twp. (excl. J.I.) $ 2,500.00/equivalent dwelling unit<br />

(min)

Hooray! Your file is uploaded and ready to be published.