Task Name Start Finish<br />

Study of main options 1 Mar '99 8 Jun '01<br />

Testing and prototyping 1 Jul '99 9 Aug '01<br />

Test beam activities 5 Jul '99 28 Jun '04<br />

Design & technical drawings 31 Mar '00 12 Oct '01<br />

Spectrometers (magnets+trackers) 31 Mar '00 9 Feb '01<br />

Target (walls+trackers+robots) 31 Mar '00 12 Oct '01<br />

Tendering and Ordering 8 Jan '01 18 Mar '02<br />

Spectrometers (magnets+trackers) 9 Feb '01 5 Oct '01<br />

Target (walls+trackers+robots) 8 Jan '01 18 Mar '02<br />

Infrastructure preparation in GS 2 Jul '01 28 Dec '01<br />

infrastructure of the OPERA detector 7 Jan '02 8 Jul '02<br />

Construction 6 Aug '01 29 Dec '03<br />

Spectrometers (magnets+trackers) 12 Oct '01 13 Dec '02<br />

Target (walls+trackers+robots) 6 Aug '01 29 Dec '03<br />

Assembly & installation 2 Sep '02 29 Oct '04<br />

Spectrometer 1 2 Sep '02 2 Jun '03<br />

Spectrometer 2 6 Jan '03 29 Sep '03<br />

Spectrometer 3 5 May '03 29 Dec '03<br />

Target Section 1 2 Jun '03 29 Dec '03<br />

Target Section 2 29 Sep '03 5 Apr '04<br />

Target Section 3 29 Dec '03 5 Jul '04<br />

Drift tubes 1 29 Dec '03 23 Feb '04<br />

Drift tubes 2 5 Apr '04 31 May '04<br />

Drift tubes 3 5 Jul '04 30 Aug '04<br />

Cabling SM1 23 Feb '04 19 Apr '04<br />

Cabling SM2 31 May '04 26 Jul '04<br />

Cabling SM3 + Robot rail 30 Aug '04 25 Oct '04<br />

Robot left 19 Apr '04 29 Oct '04<br />

Robot right 19 Apr '04 29 Oct '04<br />

Commissioning of the trackers 19 Apr '04 20 Dec '04<br />

Cosmic data taking without bricks 12 Jul '04 11 Feb '05<br />

ECC brick production 9 Mar '04 1 Apr '05<br />

ECC brick filling into the target section 5 Jul '04 23 Jun '05<br />

filling SM1 5 Jul '04 3 Jan '05<br />

filling SM2 30 Aug '04 25 Feb '05<br />

filling SM3 28 Feb '05 23 Jun '05<br />

Detector complete 23 Jun '05 23 Jun '05<br />

Target-trackers alignment 3 Jan '05 22 Jul '05<br />

Cosmic data taking with bricks 30 Aug '04 21 Jul '05<br />

CNGS beam commissioning 15 Feb '05 15 May '05<br />

Neutrino data taking starts 15 May '05 15 May '05<br />

00 2001 2002 2003 2004 2005<br />

3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3<br />

23/6<br />

15/5<br />

Figure 179: General planning for the construction of the OPERA detector.<br />