BHARAT PETROLEUM CORPORATION LTD Special Conditions of Contract<br />

CCR PROJECT , MAHUAL REFINERY- MUMBAI<br />

1.0 DEFINITIONS<br />

2.0 GENERAL<br />

Sheet 3 of 29<br />

“Consultant” shall mean Uhde India Private Ltd., (UIPL) having their office at Dugal plaza, Prem<br />

Nagar, Bibwewadi Road, Pune – 411037 , India.<br />

Engineer- in Charge shall mean Resident Construction Manager ( RCM) designated by<br />

UIPL.<br />

a) These Special Conditions of Contract (SCC) shall be read in conjunction with the General<br />

Conditions of Contract (GCC), Schedule of Rates, specifications of work, drawings and any other<br />

document forming part of this Contract wherever the context so requires.<br />

b) Notwithstanding the sub-division of the document into these separate sections and volumes, every<br />

part of each shall be deemed to be supplementary of every other part and shall be read with and<br />

into the Contract so far as it may be practicable to do so.<br />

c) If any provision in the General Conditions of Contract is repugnant to or at variance with any<br />

provision (s) of the Special Conditions of Contract and / or the Agreed Variations or if any provision<br />

of the Special Conditions of Contract is repugnant to or at variance with any provision (s) of the<br />

Agreed Variations, and the two cannot be reconciled or otherwise co-exist, then unless a different<br />

intention appears, the provision (s) of the Special Conditions of Contract shall be deemed to override<br />

the provision (s) of General Conditions of Contract and the provision (s) of the Agreed Variations<br />

shall be deemed to override the provision (s) of the Special Conditions of Contract, but only to the<br />

extent that such repugnancies in the General Conditions of Contract cannot be reconciled with the<br />

Special Conditions of Contract and / or Agreed Variations or to the extent that such repugnancies in<br />

the Special Conditions of Contract cannot be reconciled with the Agreed Variations, as the case may<br />

be.<br />

d) It will be the CONTRACTOR’s responsibility to bring to the notice of Engineer-in-Charge any<br />

irreconcilable conflict in the Contract documents before starting the work (s) or making the supply<br />

with reference to which the conflict exists.<br />

e) Wherever it is stated in this Bidding Document that such and such a supply is to be effected or such<br />

and such a work is to be carried out, it shall be understood that the same shall be effected/carried out<br />

by the CONTRACTOR at his own cost, unless a different intention is specifically and expressly stated<br />

herein or otherwise explicit from the context. Contract value (also referred to as Contract Price) shall<br />

be deemed to have included such cost.<br />

f) The materials, design and workmanship shall satisfy the applicable relevant Indian Standards,<br />

the job specifications contained herein & codes referred to. Where the job specifications<br />

stipulate requirements in addition to those contained in the standard codes and specifications,<br />

these additional requirements shall also be satisfied. In the absence of any Standard /<br />

Specifications/Codes of practice for detailed specifications covering any part of the work<br />

covered in this Bidding Document, the instructions/directions of Engineer-in-Charge will be<br />

binding on the CONTRACTOR.<br />

g) In the absence of any Specifications covering any material, design or work(s) the same shall be<br />

performed/ supplied/ executed in accordance with standard Engineering practice as per the<br />

instructions/directions of the Engineer-in-Charge, which will be binding on the CONTRACTOR.<br />

3.0 WATER AND POWER<br />

a) The clause No. 2.3 and 2.4 in Section – II (General Information about Site) of General Condition of<br />

Contract – BPCL – Refinery Division – Mahul, Mumbai regarding Water, Power and other facilities is<br />

modified to following extent:<br />

b) Water shall be provided to the CONTRACTOR at one point, subject to availability, on<br />

chargeable basis. The CONTRACTOR shall at his own cost arrange for tapping, storage tank &