BHARAT PETROLEUM CORPORATION LTD Special Conditions of Contract<br />
CCR PROJECT , MAHUAL REFINERY- MUMBAI<br />
responsibilities under this contract.<br />
Sheet 12 of 29<br />
i) Cost towards repeat tests and inspection due to failures, repairs etc. for reasons attributable to the<br />
CONTRACTOR shall be borne by the CONTRACTOR.<br />
j) Various tests as specified in specifications shall be carried out to the entire satisfaction of<br />
OWNER/UIPL.<br />
24.0 FINAL INSPECTION<br />
25.0 LEADS<br />
After completion of all tests as per specification the whole work will be subject to a final<br />
inspection to ensure that job has been completed as per requirement. If any defects are noticed<br />
in the work attributable to CONTRACTOR, these shall be attended by the CONTRACTOR at his<br />
own cost. As and when they are brought to his notice by UIPL / OWNER. UIPL / OWNER shall<br />
have the right to have these defects rectified at the risk and cost of the CONTRACTOR if he fails<br />
to attend to these defects immediately.<br />
For the various works, in case of contradiction, leads mentioned in the Schedule of Rates shall<br />
prevail over those indicated in the Technical specifications.<br />
26.0 COMPLETION DOCUMENTS<br />
Refer technical specification of the Enquiry.<br />
Also, Completion document shall contain following :<br />
• Completion Certificate by Engg. In-charge<br />
• No Demand Certificate from Contractor<br />
• No Due Certificate from Contractor<br />
• Site clearance Certificate<br />
• Labour Liability Certificate<br />
• Indemnity Bond on Rs. 100 stamp paper<br />
(Formats of above documents are enclosed as Attachment 1 ).<br />
27.0 ADDITIONAL WORKS/ EXTRA WORKS<br />
OWNER reserves their right to execute any additional works/ extra works, during the execution of<br />
Work, either by themselves or by appointing any other agency, even though such works are<br />
incidental to and necessary for the completion of Work awarded to the CONTRACTOR. In the<br />
event of such decisions taken by OWNER, CONTRACTOR is required to extend necessary<br />
cooperation, and act as per the instructions of Engineer-in-Charge. This is without prejudice to the<br />
rights of the OWNER to get the additional works/ extra works executed by the CONTRACTOR.<br />
28.0 HEALTH, SAFETY AND ENVIRONMENT (HSE) MANAGEMENT/SAFETY NORMS<br />
a) The CONTRACTOR shall adhere to the Health, Safety and Environment (HSE) Management<br />
system as per the stipulations made in the following documents :<br />
i. HSE Plan attached with SCC<br />
ii. The General Conditions of Contract