BHARAT PETROLEUM CORPORATION LTD Special Conditions of Contract<br />
CCR PROJECT , MAHUAL REFINERY- MUMBAI<br />
Sheet 11 of 29<br />
h) Contractor shall procure and stock sufficient quantities of materials adequate for the planned<br />
volume of the work during the monsoon, well in advance of the onset of same so that progress<br />
of work is not affected on this account. The Engineer-in-charge shall be free to inspect such<br />
storing arrangement (particularly at places outside of the pant areas), at any appropriate time<br />
as deemed fit by him.<br />
i) All electrical installations, equipment shall be placed on plinths above ground under proper<br />
rain shed to avoid any inundation, short circuit and hazards of electrocution.<br />
j) To maintain the standard welding quality and progress, localized welding booth in sufficient<br />
numbers as per instruction of Engineer- in charge shall be installed for protection against wind<br />
and rain.<br />
k) Contractors item rates shall be include all costs and expenses including supply of materials<br />
required for monsoon protection like tarpaulins, shed, structural, GI sheet etc. for the above<br />
provisions and no separate payment shall be made on this account.<br />
23.0 TESTS AND INSPECTION OF WORKS<br />
a) The CONTRACTOR shall carry out the various tests as enumerated in the bidding document and<br />
as per direction of Engineer-in-charge either on field or outside laboratories concerning the<br />
execution of work and supply of the material by CONTRACTOR. All the expenses shall be borne by<br />
the CONTRACTOR and shall be considered as included in the quoted price. The inspection shall be<br />
done by following:<br />
i) Third Party Inspection agency if nominated by the OWNER for all supply items (Name of<br />
the OWNER’S approved TPI agency shall be separately intimated).<br />
ii) Representative deputed by Engineer-in-charge.<br />
iii) Representative deputed by Statutory Authority.<br />
CONTRACTOR shall give prior notice sufficiently ahead of time to the Engineer-in-charge and<br />
also to the authorities/TPI to conduct inspection/ to witness such tests.<br />
b) All the tests either on the field or at outside laboratory or at any other place, concerning the<br />
execution of the work and supply of materials by the CONTRACTOR shall be carried out by the<br />
CONTRACTOR at his own cost.<br />
c) The work is subject to inspection at all times by the Engineer-in-charge. The CONTRACTOR shall<br />
carry out all instructions given during inspection and shall ensure that the work is being carried out<br />
according to the technical specifications of this bidding document, the technical documents that will<br />
be furnished to him during performance of work and the relevant codes of practice furnished to him<br />
during the performance of the work.<br />
d) The CONTRACTOR shall provide, for purposes of inspection, access ladders, lighting and<br />
necessary instruments at his own cost including Low Voltage (24V) lighting equipment for inspection<br />
of work. Compressed air for carrying out works shall be arranged by the CONTRACTOR at his own<br />
cost.<br />
e) Any work not conforming to the execution drawings, specifications or codes shall be rejected<br />
forthwith and the CONTRACTOR shall carry out the rectifications at his own cost.<br />
f) All results of inspection and test will be recorded in the inspection reports, proforma of which will be<br />
approved by the Engineer-in-charge. These reports shall form part of the Completion Documents.<br />
g) For materials supplied by OWNER, CONTRACTOR shall carryout the tests, if required by the<br />
Engineer-in-charge, and the cost of such tests shall be reimbursed by the OWNER at actual to the<br />
CONTRACTOR on production of documentary evidence.<br />
h) Inspection and acceptance of the work shall not relieve the CONTRACTOR from any of his