BHARAT PETROLEUM CORPORATION LTD Special Conditions of Contract<br />

CCR PROJECT , MAHUAL REFINERY- MUMBAI<br />

Sheet 18 of 29<br />

g) The parties hereby agree that the courts in the city of Mumbai alone shall have<br />

jurisdiction to entertain any application or other proceedings in respect of anything arising<br />

under this agreement and any award or awards made by the Sole Arbitrator hereunder shall<br />

be filed in the concerned courts in the city of Mumbai only.<br />

44.0 JURISDICTION<br />

The CONTRACTOR shall comply with the provisions of the GCC- SECTION – VIII – LABOUR<br />

LAWS & OTHER REGULATIONS Clause – 92 – JURISDICTION<br />

45.0 LIQUIDATED DAMAGES :<br />

In case of delays in completing works in the stipulated time, Owner reserves the right to<br />

recover liquidated damages at 0.5 % of the contract value for every week of delay or part<br />

there of subject to a maximum of 5 % of the total contract value until the work is<br />

satisfactorily completed and handed over. Such damages may be deducted by the Owner<br />

from any money due to the Contractor and any further amount due from the Contractor.<br />

46.0 “DEFECT LIABILITY PERIOD” in respect of:<br />

(i) Bulk Consumables shall be the date of delivery plus 6 (six) months<br />

(ii) In the case of other Material(s) shall be 18 (eighteen) months from the date of delivery<br />

or 12 (twelve) months after the same have been put in service or commissioned,<br />

whichever is earlier;<br />

(iii) In the case of altered or replaced Material(s):<br />

(a) With respect to Bulk Consumables, shall be 6 (six) months from the date of<br />

alteration, repair or replacement as the case may be; and<br />

(b) With respect to other Material(s), shall be 12 (twelve) months from the date of<br />

alteration, repair or replacement as the case may be.<br />

47.0 PERFORMANCE BANK GUARANTEE (PBG):<br />

For order value upto Rs. 10 lakh, PBG shall not be applicable.<br />

48.0 INSPECTION AND TESTING<br />

a. All imported materials shall be inspected by Third Party Inspection Agency. All major<br />

Indigenous materials shall be inspected by UIPL<br />

b. Third Party Inspection Agency where ever applicable shall be nominated by BPCL. In general<br />

the following TPIA’s are in the approved list viz. Lloyds, DNV, BV. However the bidder has<br />

option to specify in his bid the choice of the TPIA.<br />

c. In addition to any tests to be conducted by the Vendor under the Contract or any applicable<br />

codes or standards, the Material(s) shall be subject to inspection and/or testing by<br />

Inspector(s) (including Third Party Inspector(s)) at any time prior to shipment and/or despatch<br />

and to final inspection within a reasonable time after arrival at the Project Site. The<br />

Inspector(s) shall have the right to carry out the inspection or testing, which will include<br />

inspection and testing of the raw materials at manufacturers shop, at fabricators shop and at<br />

the time of actual despatch before and/or after completion of packing.<br />

d. In addition to testing and inspection by Inspectors, BPCL may nominate an institutional agency<br />

like Boiler-Inspectorate for official testing of coded equipment. The Vendor shall ensure that<br />

all procedures for preparation and performance of tests prescribed by such institution shall be<br />

scrupulously complied and observed.