PPC Riebeeck West: Storm water Management Plan Page 9<br />
1.5 OVERVIEW OF MINING OPERATIONS<br />
1.5.1 EXISTING FACILITY<br />
The purpose of this section is to provide the reader with a brief description of the activities<br />
taking place at Riebeeck <strong>and</strong> to ensure that the environmental management measures (in<br />
Section 6) can be assigned to specific activities.<br />
The description of the activities is linked to the organisational flow of the <strong>mine</strong>. The<br />
organisational flow includes the core processes which are:<br />
Mining<br />
Production<br />
Packaging <strong>and</strong> logistics (dispatch of product)<br />
In addition to the core processes, PPC Riebeeck have the following supporting processes:<br />
Quality assurance<br />
Risk management (including environmental management)<br />
Engineering<br />
Administration / Stores<br />
Organisational performance.<br />
The description of the activities has been provided in a chronological order which follows the<br />
mining of the limestone, shale, s<strong>and</strong> <strong>and</strong> clay through to production <strong>and</strong> dispatch of the clinker /<br />
<strong>cement</strong> from the plant, followed by a description of the supporting services to ensure the<br />
smooth operation of the <strong>mine</strong>. This section describes both the existing operations <strong>and</strong> the<br />
intended <strong>cement</strong> expansion project.<br />
The description of the activities is interlinked into the PPC Riebeeck aspect register which was<br />
developed for the implementation of the ISO 14001:2004 environmental management system.<br />
The following figures have been provided to assist in the readers underst<strong>and</strong>ing of the<br />
description of the activities that take place on the site:<br />
Figure 1.4 provides a diagrammatic indication of the overall process that takes place on<br />
the site. This diagram is interlinked into the organisational flow at Riebeeck.<br />
Figure 1.5 provides an aerial photograph of the whole of the site.<br />
Figure 1.6 provides an aerial photograph of the current plant area <strong>and</strong> a brief<br />
description of the function of each building.