Water Sensitive Urban Design<br />
Bioretention Basin Sign-Off Forms<br />
Development stage:<br />
Bioretention basin ID:<br />
Pre-Start Construction Meeting<br />
Location:<br />
Date:<br />
List of Attendees<br />
Name Discipline (suggested) Company<br />
1 Developer<br />
2 Site superintendent (civil)<br />
3 Site superintendent (landscape)<br />
4 Civil Contractor<br />
5 Landscape Contractor<br />
6 <strong>WSUD</strong> - Design Engineer<br />
7 Civil Engineer<br />
8 Landscape Architect<br />
9<br />
Checklist of Sign-Off Forms<br />
Sign-Off Form<br />
Date Completed<br />
Form A<br />
Form B<br />
Form C<br />
Form D<br />
Earthworks and Hydraulic / Functional Structures<br />
Erosion and Sediment Control<br />
Filter Material and Finished Levels<br />
Landscape Planting (Macrophyte and Inlet Zone)<br />
Construction Tolerances:<br />
The construction tolerances on the bioretention systems are to be:<br />
••<br />
plus or minus 50 mm on earth works and filter media levels.<br />
••<br />
plus or minus 25 mm on hydraulic structures (e.g. pit and weir<br />
crests/ bund heights, pipe and pit invert levels)<br />
Deviations to be approved only at the discretion of superintendent.<br />
50 <strong>Book</strong> 4 | MAINTENANCE