27.04.2014 Views

Landcom Book 4 Maintenance - WSUD

Landcom Book 4 Maintenance - WSUD

Landcom Book 4 Maintenance - WSUD

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Water Sensitive Urban Design<br />

Bioretention Basin Sign-Off Forms<br />

Development stage:<br />

Bioretention basin ID:<br />

Pre-Start Construction Meeting<br />

Location:<br />

Date:<br />

List of Attendees<br />

Name Discipline (suggested) Company<br />

1 Developer<br />

2 Site superintendent (civil)<br />

3 Site superintendent (landscape)<br />

4 Civil Contractor<br />

5 Landscape Contractor<br />

6 <strong>WSUD</strong> - Design Engineer<br />

7 Civil Engineer<br />

8 Landscape Architect<br />

9<br />

Checklist of Sign-Off Forms<br />

Sign-Off Form<br />

Date Completed<br />

Form A<br />

Form B<br />

Form C<br />

Form D<br />

Earthworks and Hydraulic / Functional Structures<br />

Erosion and Sediment Control<br />

Filter Material and Finished Levels<br />

Landscape Planting (Macrophyte and Inlet Zone)<br />

Construction Tolerances:<br />

The construction tolerances on the bioretention systems are to be:<br />

••<br />

plus or minus 50 mm on earth works and filter media levels.<br />

••<br />

plus or minus 25 mm on hydraulic structures (e.g. pit and weir<br />

crests/ bund heights, pipe and pit invert levels)<br />

Deviations to be approved only at the discretion of superintendent.<br />

50 <strong>Book</strong> 4 | MAINTENANCE

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!