Water Sensitive Urban Design<br />

Hold Point - Sign off is required from superintendent and bioretention basin designer before proceeding<br />

Functional and hydraulic functions<br />

Inlet and outlet pipes and headwalls correctly set<br />

out and at correct level (upstream and downstream<br />

ends)<br />

Bypass weir correct width and level<br />

Overflow pit is correct size and crest is at correct<br />

level<br />

<strong>Maintenance</strong> pipe and valve installed at<br />

correct location and level<br />

<strong>Maintenance</strong> access installed to inlet zone<br />

Rock or concrete base constructed at<br />

inlet to bioretention basin<br />

Rock protection provided at correct locations<br />

and rock size consistent with design<br />

Hold Point - Sign off is required from superintendent and bioretention basin designer before proceeding<br />

Under-drainage<br />

Base of system free from debris<br />

Under-drainage pipes laid at required grade<br />

(verified using level or string line)<br />