Water Sensitive Urban Design<br />

Sedimentation Basin Sign-Off Forms<br />

Development stage:<br />

Sediment basin / pond ID:<br />

Pre-Start Construction Meeting<br />

Location:<br />

Date:<br />

List of Attendees<br />

Name Discipline (suggested) Company<br />

1 Developer<br />

2 Site superintendent (civil)<br />

3 Site superintendent (landscape)<br />

4 Civil Contractor<br />

5 Landscape Contractor<br />

6 <strong>WSUD</strong> - Design Engineer<br />

7 Civil Engineer<br />

8 Landscape Architect<br />

9<br />

Checklist of Sign-Off Forms<br />

Sign-Off Form<br />

Date Completed<br />

Form A<br />

Form B<br />

Form C<br />

Form D<br />

Earthworks and Hydraulic / Functional Structures<br />

Sediment and Erosion Control<br />

Topsoil and Finished Levels<br />

Landscape Planting (Macrophyte and Inlet Zone)<br />

Construction Tolerances:<br />

The construction tolerances on the constructed wetland systems are to be:<br />

••<br />

plus or minus 25 mm on hydraulic structures (e.g. pit and weir crests/ bund heights, pipe and pit invert<br />

levels)<br />

••<br />

plus or minus 50 mm on earthworks (base of wetland, as measured from the surface of the topsoil).<br />

••<br />

plus or minus 50 mm on embankments and bunds (that is, crest level of the embankment).<br />

Deviations to be approved only at the discretion of superintendent.<br />