Water Sensitive Urban Design<br />

Form A – Earthworks and Hydraulic/Functional Structures<br />

Purpose:<br />

5) To ensure bulking out and key levels of hard structures are in accordance with design specifications.<br />

6) To ensure hydraulic structures associated with the sedimentation basin or pond is constructed in<br />

accordance with the design specifications.<br />

Checklist:<br />

Items<br />

Checked<br />

Satisfactory<br />

Action/s<br />

(if required)<br />

Actions<br />

addressed<br />

(initial)<br />

Bulking out & hard structures<br />

As constructed survey of basin base and surrounding<br />

bunds, pit crests, inlet and outlet pipes<br />

Base levels are at correct elevation, given the<br />

minimumallowances for topsoil and impervious<br />

liner (where required)<br />

Hold Point - Sign off is required from superintendent and wetland designer before proceeding<br />

Bunds and impervious liner<br />

Laboratory test results of liner material submitted<br />

and adequate<br />

Delivery docket of liner material submitted<br />

and adequate<br />

Delivery docket of liner material supplied<br />

Geotechnical engineer certification / sign off<br />

of key bunds<br />

Hold Point - Sign off is required from superintendent and wetland designer before proceeding<br />

70 <strong>Book</strong> 4 | MAINTENANCE