Water Sensitive Urban Design<br />
Finished levels<br />
As constructed survey of basin surface and<br />
surrounding bunds completed<br />
Final constructed levels are consistent with<br />
design levels<br />
Under-drainage pipes flushed to remove initial<br />
ingress of material<br />
All civil construction items are complete and basin is<br />
ready for planting by landscape contractor<br />
Geofabric layer + 50mm topsoil (top layer of<br />
supplied filter material) and turf applied to basin<br />
surface.<br />
Suitable batter protection in place<br />
(e.g. sediment fence or landscape netting)<br />
HOLD POINT - Sign off is required from superintendent and bioretention basin designer before proceeding<br />
Comments<br />
Signed by Superintendent(s):<br />
Print Name:<br />
Date:<br />
56 <strong>Book</strong> 4 | MAINTENANCE