Technology-Specific Assumptions<br />

The technology-specific assumptions comprise assumptions for domestic boilers, industrial boilers and for the CHP<br />

turbine. The assumptions for these technologies are outlined in Tables 5, 6 and.7.<br />

Table 5: Domestic Boiler Assumptions<br />

Parameter Unit Pellet Boiler NG Boiler Light Oil Boiler<br />

Full load operation hours H 1,000 1,000 1,000<br />

Installed thermal capacity MW 0.020 0.020 0.020<br />

Heat generation MWh/year 20,000 20,000 20,000<br />

Heat efficiency % 90 108 90<br />

Total investment € 6,300 3,412.5 3,900<br />

Specific investment in heating boiler 1000 €/MW 470 565.92 646.77<br />

Investment subsidy ( 1 ) 1000 € 6.300 0 0<br />

Maintenance costs per year 1000 € per MW 21.559 12.935 43.118<br />

Maintenance costs per year % of inv. 2.424 2.286 6.667<br />

Note 1 Greener Homes Scheme, Application Guide, Ver 1.4.<br />

In an attempt to represent the market segment of biomass boilers in commercial buildings, small industry and<br />

institutions, a comparison was furthermore made between a 100 kW wood chip boiler and a conventional natural gas<br />

boiler or an oil fired boiler. The assumptions regarding investments (including subsidy) and maintenance costs are<br />

shown in Table 6.<br />

Table 6: Industrial Boiler Assumptions<br />

Parameter Unit Wood Boiler ( 1 ) NG Boiler ( 1 ) Oil Boiler ( 2 )<br />

Full load operation hours H 6,000 6,000 6,000<br />

Installed thermal capacity MW 5 5 5<br />

Heat generation MWh/year 30,000 30,000 30,000<br />

Heat efficiency % 108 101 95<br />

Specific investment in boiler 1000 €/MW 565 350 350<br />

Investment subsidy ( 3 ) 1000 € 621.5 0<br />

Total investment 1000 € 2203.5 1,750 1,750<br />

Maintenance costs per year 1000 € per MW 66.105 52.5 52.5<br />

Maintenance costs per year % of initial inv. 3 3 3<br />

Note 1 “Technology data for electricity and heat generating plants”, Danish Energy <strong>Authority</strong>, 2004.<br />

Note 2 It is assumed that investment and maintenance costs for the industrial oil boiler are the same as those for the gas boiler<br />

Note 3 Renewable Heat Deployment Programme Application Guide, Ver 1.1.<br />

112<br />