Version1: Applicable from 1 April 2011 - Transnet
Version1: Applicable from 1 April 2011 - Transnet
Version1: Applicable from 1 April 2011 - Transnet
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
2.1.11. Once nominated, a vessel or representative must submit to the relevant<br />
CPO a written update of her ETA on the, 10 th, 7 th , 5 th , 4 th , 3 rd , 2 nd , and last day prior<br />
to her ETA. The day on which the ETA falls is excluded <strong>from</strong> the computing of the<br />
number of days. At day five (5) <strong>from</strong> ETA, the vessel must be firm and once firm,<br />
the planned berth will be confirmed by TPT. It will not be necessary for a vessel<br />
which arrives early to submit a daily update provided that the arrival update<br />
indicates final notice of vessel arrival. Such vessel will, however, still be treated on<br />
the basis of an early arrival and planned in accordance with clause 4. The early<br />
nomination of vessels serves a dual purpose to initiate cargo forward planning for<br />
the vessel and for the preliminary terminal planning and allocation of berths.<br />
2.1.12. The firm nomination notice update of five (5) days as specified in clauses 2.1.10 and<br />
2.1.11 above must be clearly endorsed as such, and unless specified elsewhere in<br />
these TOGs, will be the source information used by TPT in establishing vessel<br />
seniority. Any subsequent “firming” notices received for a vessel will simply serve as<br />
an ETA update and such vessel will be treated as either an early or late arrival.<br />
2.1.13. Vessels arriving on the same or following day within the same eight (8) hour window<br />
will at the discretion of TPT be treated on the basis of first come, first served, and<br />
the physical arrival at Port limits/outer anchorage will be factors taken into<br />
consideration in determining an outcome. The allocation of the berth will in any<br />
event take into consideration the factors of clause 2.2 which will guide any decisions<br />
in this regard.<br />
2.1.14. A vessel needing to either increase or decrease cargo or make changes to the cargo<br />
mix at the request of owners/ charterers may do so but only up until the time of<br />
firming of a vessel and provided that these changes do not impact materially by<br />
more than eight (8) hours on the scheduled window, which time includes for the<br />
vessel to close hatches and vacate the berth. Any increases beyond and eight (8)<br />
period will be subject to Terminal approval in order to minimise any impact<br />
prejudicing any other scheduled vessel.<br />
2.1.15. Vessels may be substituted <strong>from</strong> time to time provided that:<br />
2.1.15.1. the vessel for substitution is presented to TPT for consideration and approval;<br />
2.1.15.2. the vessel and cargo characteristics of the vessel presented for substitution does<br />
not differ <strong>from</strong> those of the vessel to be substituted;<br />
2.1.15.3. should the vessel and cargo characteristics of the vessel presented for<br />
substitution differ <strong>from</strong> those of the vessel to be substituted, the vessel<br />
presented for substitution may, at the sole discretion of TPT, be accepted<br />
provided TPT is satisfied that its cargo working can be managed within the<br />
limitations of the original berthing window and berth.<br />
Terminal Operating Guidelines: Version 3 – <strong>Transnet</strong> Port Terminals Ro-Ro, Break-bulk, Bulk and Agricultural Terminals: 1 <strong>April</strong> 2013<br />
TRANSNET PORT TERMINALS, A DIVISION OF TRANSNET SOC Ltd 14