27.10.2014 Views

Version1: Applicable from 1 April 2011 - Transnet

Version1: Applicable from 1 April 2011 - Transnet

Version1: Applicable from 1 April 2011 - Transnet

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

12.3.2.4.1. in consultation with the lines, which vessel should be given priority<br />

based on suitable berth availability, cargo availability, terminal<br />

capacity, vessel working hours and any other information deemed<br />

relevant.<br />

12.3.2.4.2. Should no agreement arise pursuant to clause 12.3.2.3.1 the vessel<br />

with first NOR (arrival time) as recorded by Port Control - TNPA will<br />

be given priority, where both vessels are deemed to be unplanned.<br />

12.3.3. Phase II Planning<br />

12.3.3.1. Phase II’s will be held in accordance with the following guidelines and the<br />

information set out below must be sent to the CPO prior to the Phase II:<br />

12.3.3.1.1. The Ro-Ro Terminal Provisional Phase II Document must be submitted<br />

to the Ro-Ro CPO during office hours, five (5) days prior to arrival.<br />

12.3.3.1.2. A provisional booking list, detailing all cargo, including any High, Heavy<br />

and/or static units must be supplied five (5) days prior to vessel<br />

arrival. Such booking list must be updated on a daily basis.<br />

12.3.3.1.3. The discharge sequence of cargo and manifests must be supplied to<br />

the CPO three (3) working days prior to the vessel’s arrival.<br />

12.3.3.1.4. A Pre-load plan / load sequence plan must be supplied together with<br />

the Phase I (5 day firm nomination). A final Pre-load plan / load<br />

sequence Plan must be supplied 24 hours prior to the Phase II.<br />

12.3.3.1.5. Phase II’s will be held on Monday – Friday at 14h00, on the day prior<br />

to the vessel’s arrival. Should a vessel plan to arrive on a Sunday or<br />

Monday, the Phase II meeting will be held on the preceding Friday<br />

using provisional figures, with final figures being confirmed and<br />

electronically mailed to attendees at an agreed upon scheduled cut-off<br />

time for this information.<br />

12.3.3.1.6. Phase II’s will not be held on 1 May, 25 December and 1 January of<br />

each year, or on any Saturdays or Sundays.<br />

12.3.3.2. At the Phase II, the following matters will be discussed and recorded in the<br />

Phase II minute and all previous information and documentation supplied<br />

must be updated accordingly:<br />

12.3.3.2.1. The confirmed berth allocation;<br />

12.3.3.2.2. Cargo volumes cleared for discharging and loading including the<br />

following information as supplied by the Line:<br />

12.3.3.2.3. The number of new units;<br />

Terminal Operating Guidelines: Version 3 – <strong>Transnet</strong> Port Terminals Ro-Ro, Break-bulk, Bulk and Agricultural Terminals: 1 <strong>April</strong> 2013<br />

TRANSNET PORT TERMINALS, A DIVISION OF TRANSNET SOC Ltd 58

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!