CH2M HILL<br />
SUMMARY - ALTERNATIVE COST ESTIMATE SUMMARY<br />
PROJECT:<br />
<strong>Franklin</strong> <strong>Boulevard</strong> <strong>Study</strong><br />
DATE:<br />
SHEET:<br />
DESIGN LEVEL:<br />
Planning<br />
6/19/2009 1 <strong>of</strong> 7<br />
Alternative Right-<strong>of</strong>-Way Impacts (sf) Rank<br />
Private Property/ Business Impacts<br />
LOW MEDIUM HIGH<br />
Project Cost<br />
Rank<br />
Multi-Way Center<br />
Multi-Way South<br />
Arterial Center<br />
Arterial South<br />
14th Ave. Arterial<br />
14th Ave. Multi-Way<br />
430,540 5 0-3 4-6 20-25 $13,100,000 5<br />
418,150 4 0-2 1-3 18-24 $13,100,000 5<br />
235,810 1 0-2 2-5 14-18 $7,500,000 2<br />
238,800 2 2-3 2-3 12-14 $7,500,000 2<br />
356,330 3 3-4 3-5 15-20 $7,200,000 1<br />
497,250 6 3-6 4-6 20-28 $12,600,000 4<br />
― Items Included In This Estimate:<br />
Engineering Design & Construction Fees<br />
New Asphalt Concrete and Aggregate Base<br />
Excavation / Embankment<br />
Pavement Markings<br />
Concrete Curbs<br />
Sidewalks<br />
Drainage<br />
Erosion Control<br />
Illumination<br />
Traffic Signals<br />
Landscaping<br />
Mobilization<br />
Contingency<br />
McVay Intersection is not being addressed at this time.<br />