CH2M HILL<br />

SUMMARY - QUICK COST ESTIMATE<br />

PROJECT: <strong>Franklin</strong> <strong>Boulevard</strong> <strong>Study</strong>:<br />

<strong>Franklin</strong>/McVay Intersection -<br />

DESIGN LEVEL:<br />

KIND OF WORK:<br />

Roundabout<br />

Planning<br />

Roadway<br />

PREPARED BY:<br />

Billy Adams / 503.235.5000<br />

LENGTH (MILE):<br />

0.50<br />

DATE:<br />

6/19/2009<br />

SHEET:<br />

1 <strong>of</strong> 1<br />

NO. ITEM<br />

UNIT QUANTITY UNIT COST COST<br />

1 Curb, Gutter, Sidewalks & Drainage Mi. 0.50 $1,097,900.00 $547,910<br />

2 Bike <strong>Boulevard</strong><br />

Mi. $140,600.00 $0<br />

3 New Roadway<br />

Lane-Mi. 2.9 $358,200.00 $1,040,476<br />

4 Overlay Existing Roadway<br />

Lane-Mi. $61,300.00 $0<br />

5 Reconstruct Existing Roadway Lane-Mi. $107,100.00 $0<br />

6 Restriping Existing Roadway<br />

Lane-Mi. $8,700.00 $0<br />

7 Interconnect Signal<br />

LS $35,000.00 $0<br />

8 New Signal<br />

EA $250,000.00 $0<br />

9 Signal Modifications<br />

EA $65,000.00 $0<br />

10 Transit Enhancements<br />

EA $25,000.00 $0<br />

11 Traffic Calming<br />

5-10% - $0<br />

12 Illumination<br />

Mi. 0.50 $260,000.00 $129,754<br />

13 Landscaping<br />

Mi. 0.63 $235,000.00 $149,189<br />

14 Bridges<br />

SF $0<br />

15 Walls<br />

SF $50.00 $0<br />

16 Concrete Islands<br />

SF 13,780<br />

SUBTOTAL<br />

$12.00 $165,360<br />

$2,032,690<br />

ADDITIONAL CONST. COSTS SUGGESTED PERCENTAGE<br />

COST<br />

Construction Surveying<br />

1.0-2.5% 2.5% $50,800<br />

TP & DT<br />

3.0-8.0% 8.0% $162,600<br />

Mobilization<br />

8.0-10.0% 10.0% $203,300<br />

Erosion Control<br />

0.5-2.0% 2.0% $40,700<br />

Contingency<br />

30-40% 40.0% $813,100<br />

Escalation (per year)<br />

Design Year<br />

Construction Year<br />

0.5-2.0%<br />

2008 $0<br />

$0<br />

TOTAL CONSTRUCTION COST<br />

$3,303,190<br />

RIGHT OF WAY<br />

UNIT QUANTITY<br />

Right <strong>of</strong> Way Acquisition<br />

SF 499,374<br />

Business Acquisition<br />

High EA 10<br />

Medium EA 4<br />

ENGINEERING COSTS SUGGESTED PERCENTAGE<br />

COST<br />

Design Engineering<br />

13.0% 13.0% $429,400<br />

Construction Engineering<br />

10.0% 10.0% $330,300<br />

TOTAL PROJECT COST<br />

Assumptions:<br />

Based on 2007 Dollars<br />

Existing Roadway Will Be Removed<br />

Supporting BRT Features Are Not Included (Shelters, Signing, etc.)<br />

Used for Comparsion <strong>of</strong> Signal vs. Roundabout Only<br />

$4,100,000