Tender No DRM/S&T(ADI)/ Tele/ 02 of 2012-13<br />
Chapter – II – Special Condition of Contract<br />
2.17 INSPECTION <strong>OF</strong> WORKS:<br />
The Engineer In-charge or his authorized representative may inspect and test the<br />
various portions of the work at all stages and shall have full power to reject all or<br />
any portion of the work that he may consider to be defective or inferior in quality<br />
of materials, workmanship or design in comparison to what is called for in the<br />
specification. In the event of rejection of any work already executed and not in<br />
accordance with specification as in this tender and / or as determined by the<br />
Engineer or which the Contractor has been apprised, the Contractor shall carry<br />
out alterations/replacements to such works to the satisfaction of the Engineer Incharge<br />
of the work for which no additional payment will be borne by the<br />
Railways.<br />
2.18 INSPECTING <strong>OF</strong>FICER – POWER <strong>OF</strong> REJECTION<br />
The supply portion of work wilI be inspected by ADSTE/ADI or any<br />
representative of DRM(S&T) ADI as nominated to realize the end objective. The<br />
execution portion will be inspected by respective Sectional officer or any<br />
representative of DRM(S&T) ADI as nominated to realize the end objective.<br />
Power of rejection:-<br />
(i)<br />
(ii)<br />
(iii)<br />
(iv)<br />
To reject any items submitted as not being in accordance with the tendered<br />
technical specification.<br />
To reject the whole of the installation offered for inspection, if after inspection the<br />
inspection authority is satisfied that the material offered for inspection is<br />
unsatisfactory.<br />
To mark the rejected stores with a rejection mark, so that they can be easily<br />
identified if resubmitted.<br />
The inspecting officer’s decision as regards the rejection shall be final and<br />
binding on the contractor.<br />
Note- The contractor shall arrange, when so required, suitable means of transport<br />
for inspection of material/ work sites by officer nominated for this purpose on<br />
the days mutually decided.<br />
2.19 CONSIGNEE’S RIGHT <strong>OF</strong> REJECTION:<br />
(i)<br />
Notwithstanding any approval which the inspecting officer may have given in<br />
respect of the stores or any materials or the work or workmanship involved in the<br />
performance of the contract (Whether with or without any test carried out by the<br />
contractor or the Inspecting officer or under the direction of the Inspecting<br />
officer) and notwithstanding delivery of the stores where so provided to the<br />
Divisional Railway Manager (S & T) Ahmedabad-45<br />
For & on behalf of the president of India<br />
Chapter- II Page 15 of 32