Tender No DRM/S&T(ADI)/ Tele/ 02 of 2012-13<br />

Chapter – II – Special Condition of Contract<br />

2.35 PART COMMISSIONING<br />

If the works are not completed as per the programme of work and there is<br />

deviation from the milestones to be achieved Railways will be free to make use of<br />

the partially commissioned work. Making such use of partially commissioned<br />

work will not be deemed as provisional acceptance from the Railways.<br />

2.36 PLACING IN SERVICE AND MAINTENANCE<br />

(i)<br />

After the equipment has been commissioned and placed in service and Provisional<br />

Acceptance Certificate is issued by the Engineer in-charge, the contractor shall be<br />

responsible for proper maintenance of the equipment for a period of one year of<br />

schedule ‘A’ & ‘B’ from the date of issuing of the provisional acceptance<br />

certificate. For this purpose he shall prepare a maintenance plan and make<br />

available the services of qualified maintenance engineers for a prompt service.<br />

(ii) Service engineers for maintenance shall normally be out of those engineers<br />

associated with the execution of the work. Details of the Service<br />

Personnel/Engineers (Bio-data and experience) proposed to be associated with<br />

maintenance, shall be furnished by the Contractor to the Railways, well in advance<br />

of the commencement of the maintenance period. Changes, if any on special case<br />

shall be with the specific approval of Engineer in-charge.<br />

(iii)<br />

(iv)<br />

The team will comprise of atleast one Maintenance Engineer and other supporting<br />

staff (preferably located at Ahmedabad ). Maintenance Engineers will be stationed<br />

at the location approved by Engineer in-charge and Contractor will make sure that<br />

they can be easily contacted through telephones/Cell Phones at any time.<br />

If any lacuna is noticed in the functions as a result of any defect in configuration or<br />

manufacture, the same will be rectified by the contractor free of cost. During such<br />

rectification if any faulty equipment/modules need replacement or repair, they<br />

shall be provided by the contractor from the set of equipment or modules that the<br />

contractor should bring to the site of installation in addition to all the materials to<br />

be supplied against this contract. Use of spare modules covered under the schedule<br />

of material of this tender shall not be permitted to be used during installation,<br />

commissioning and during the period of maintenance/supervision for thirty six<br />

months.<br />

2.37 WARRANTY and MAINTENANCE PERIOD UNDER WARRANTY:<br />

The contractor shall warrant that every equipment shall be free from defects and<br />

faults in design, materials, workmanship and manufacture and shall be of highest<br />

grade and consistent with the established and generally accepted standards for<br />

goods of the type ordered. The warranty of materials/works schedule ‘A’’ 12<br />

Divisional Railway Manager (S & T) Ahmedabad-45<br />

For & on behalf of the president of India<br />

Chapter- II Page 23 of 32