Description<br />
Status<br />
34 months Design and build two transducers <strong>for</strong> 14” diameter<br />
center zone. Evaluate per<strong>for</strong>mance on 14” chord<br />
block. (PW with support from GE)<br />
(30<br />
months)<br />
(33<br />
months)<br />
(39<br />
months)<br />
(42<br />
months)<br />
(48<br />
months)<br />
10” diameter phased array,(go/no go decision<br />
at 30 months)<br />
(Critical review with FAA, seek program redirection<br />
to develop phased arrays) (All)<br />
Complete preliminary phased array surveys. (PW)<br />
Evaluate up to three candidate phased array<br />
systems.<br />
Identify preferred configuration <strong>for</strong> factory<br />
evaluation system.<br />
Design and build improved phased array<br />
transducer assembly.<br />
Factory <strong>Evaluation</strong> / Demonstration<br />
36 months* 44 months Complete factory test of five heats. Conduct<br />
industry demonstration of #1FBH capability in 10”<br />
diameter. (GE, PW)<br />
38 months* 46 months Evaluate indication finds from factory test,<br />
document results. (GE, PW, ISU).<br />
40 months 48 months Report of laboratory and factory evaluations<br />
including sensitivity data <strong>for</strong> use by the Inspection<br />
Systems Capability Working Group and cost<br />
comparisons <strong>for</strong> the different inspection<br />
approaches. (All)<br />
Large diameter billet<br />
12 months Build chord calibration standard <strong>for</strong> 14” diameter,<br />
near-center region. (PW)<br />
18 months 20 months Evaluate capability on 13” and 14” diameter using<br />
conventional and zoned fixed focus, determine<br />
improvement over conventional. Provide data to<br />
3.1.1 <strong>for</strong> model validation and POD estimation <strong>for</strong><br />
large diameter billet. (GE, PW, ISU)<br />
20 months 24 months Laboratory assessment of sensitivity at diameters<br />
greater than 10" diameter using fixed focus<br />
transducers. (All)<br />
General issues<br />
28 months Complete attenuation compensation procedure in<br />
cooperation with 3.1.1. (ISU with support from PW<br />
and GE)<br />
30 months Procedures to account <strong>for</strong> attenuation effects that<br />
occur in titanium billet and thus improve the POD of<br />
billet inspection. (All)<br />
Original<br />
Date<br />
Revised<br />
Date<br />
Description<br />
Transducer order has been placed.<br />
Complete<br />
13” billet inspection complete at GE<br />
14” chord block inspection complete<br />
Complete at P&W<br />
Status<br />
60 months Provide revision of AMS 2628 titanium billet<br />
specification to SAE Committee K.<br />
60 months Calibration standards including 14" diameter chord<br />
block and transducers (fixed focus and phased<br />
array assemblies) as needed.<br />
Quarterly Report – January 1, 2002 –March 31, 2002<br />
print date/time: 6/6/2002 - 8:39 AM – Page 32