192 <strong>ITEM</strong> ToolKit Getting Started Guide<br />

F-Vesely<br />

The F-Vesely (Fussell-Vesely) importance measure represents an event’s contribution to the system unavailability.<br />

Increasing or decreasing the availability of events with a higher importance value will have the most significant effect on<br />

system availability.<br />

Birnbaum<br />

The Birnbaum measure for an event represents the sensitivity of system unavailability with respect to changes in the events<br />

unavailability.<br />

B-Proschan<br />

The B-Proschan (Barlow-Proschan) event importance measure takes into consideration the sequence of event failures within<br />

its calculation. It is the probability that the system fails because a critical cut set containing the event fails, taking into<br />

consideration that the event fails last.<br />

How to Display a Critical Path<br />

1. Select the Analysis pull-down menu and click on Critical Path. The Critical Path window displays:<br />

2. From this window you can select the Critical Path importance level you wish to use, add and delete levels, check all<br />

levels, uncheck all levels, and use the color palette to assign a color to a specific level.