FIRST LINE<br />

BUSINESS-ACCENT<br />

In the area of project implementation is the<br />

largest in the region number of representatives<br />

of indigenous minority peoples of the North –<br />

about 11 thousand people, half of whom lead a<br />

nomadic lifestyle. Gazpromneft-Yamal, provides<br />

financial assistance to the nomads who are in a<br />

difficult life situation, involves in various social<br />

projects and organization of air traffic and deliver<br />

food in remote areas.<br />

New approaches to the Arctic<br />

Applying of new technologies for the efficient<br />

and safe oil production in the permafrost is<br />

one of the key priorities of the company. On<br />

June, 2016, Gazprom Neft adopted a program<br />

"the development of fields in difficult climatic<br />

and geographical conditions" in the overall<br />

technological strategy of the unit of exploration<br />

and production. The objective of the program is<br />

to fix the best practices that are already applied<br />

in building on the various company projects, to<br />

select and test new technologies, and prepares<br />

model solutions for major building projects<br />

which will reduce the time searching for the right<br />

technology and to reduce the errors.<br />

Working in difficult climatic conditions is not news<br />

for oil and gas companies. Large deposits today,<br />

as a rule, are not located in the most accessible<br />

locations. Harsh climate, long distances to the<br />

nearest shelter, and problems with the transport<br />

infrastructure – all this can result to large<br />

difficulties for their settlement, and hence costly.<br />

As noted in the company, any extra ton of cargo<br />

becomes critical if you need to deliver thousands<br />

of kilometers on ice roads and incorrect logistics<br />

decisions can lead to a repeated growth of the<br />

already considerable expenses.<br />

Novy Port and Messoyakha are implemented<br />

in the permafrost zone. As explained by the<br />

specialists of Gazprom Neft: the soil here<br />

for thousands of years is in a frozen state,<br />

and the heat from the constructed facilities<br />

should not lead to thawing, otherwise the<br />

ground will "float" and begin to sink, damaging<br />

and destroying structures. To comply with<br />

temperature balance, the pipeline lay not in the<br />

ground and on supports. It is important that<br />

heat from the chimney, at which there is hot oil<br />

is not transferred into the ground. Therefore,<br />

the pipelines under the supports provided with<br />

stabilizers special tubes, collecting the heat<br />

from the soil into the environment. Buildings and<br />

tankers in these regions also erected on stilts<br />

and rose above the ground so that heat is not<br />

transmitted to the ground.<br />

As noted in the company, the cost of building<br />

the pipeline is affected by many different factors:<br />

FACTS<br />

5.6 mln<br />

is the peak of extraction up<br />

to 2020<br />

89.2 mln<br />

tons Gazprom plans to<br />

extract in 20<strong>17</strong><br />

pipe material, design of supports,<br />

the thickness of the insulation<br />

layer, the use of electrical heating<br />

systems, selection of the optimal<br />

lengths of the pipeline. So in the<br />

construction of pressure pipeline<br />

on Messoyakha, the use of pipe<br />

material of higher strength class<br />

allowed to reduce the total cost<br />

of construction: decreased metal<br />

consumption, the weight of the<br />

pipe, thereby reducing the number<br />

of supports and to save on<br />

construction and installation works<br />

and delivery of the equipment.<br />

Gazprom Neft gives an example<br />

of saving on material in the<br />

framework of the project on the<br />

Novoportovskoe field. When<br />

laying pipelines on the multiple<br />

well platforms, usually used<br />

radial scheme where each well<br />

to measuring node is a separate<br />

pipe. But in permafrost regions<br />

they are located above ground on<br />

poles and it dramatically increases<br />

the consumption of the materials<br />

and the cost of the entire facility.<br />

“As a solution to problems of<br />

Novy Port was proposed and<br />

considered two-pipe system,<br />

consisting of a single tube of the<br />

collector and one test line. This<br />

scheme requires an increasing the<br />

number of valves, but it simplifies<br />

the site of the metering installation<br />

and significantly reduces the<br />

consumption of the whole system.<br />

In the future construction pads<br />

on permafrost will be carried out<br />

according to this scheme," said the<br />

company.<br />

One more direction of<br />

development of Arctic technologies<br />

is the use of the construction at<br />

oil production facilities finished<br />

modular blocks, allowing fast<br />

assembly in cold climate.<br />

According to the experts, currently,<br />

many pumping stations, canteens,<br />

administrative complexes,<br />

dormitories and many more<br />

are delivered as complete units<br />

with all necessary equipment.<br />

Using new approaches and<br />

technologies Gazprom Neft today<br />

is successfully developing the<br />

Russian Arctic.<br />