To ensure power system reliability of subsystem areas in terms of generation,<br />

transmission, and distribution, 2 areas which have high possibilities of power shortages were<br />

considered thoroughly.<br />

Ensuring power system reliability in Southern of <strong>Thailand</strong><br />

<strong>Power</strong> demand in southern of <strong>Thailand</strong> would grow 3 percent annually; therefore,<br />

3 power plants will be added during 2019-2024 as the followings:<br />

In 2019, Krabi Coal-fired <strong>Power</strong> <strong>Plan</strong>t<br />

In 2021, Thepa Coal-fired <strong>Power</strong> <strong>Plan</strong>t unit 1<br />

In 2024, Thepa Coal-fired <strong>Power</strong> <strong>Plan</strong>t unit 2<br />

800 MW<br />

1,000 MW<br />

1,000 MW<br />

Ensuring power system reliability in Metropolitan area and<br />

central of <strong>Thailand</strong><br />

Electricity consumption of metropolitan area - the country’s largest economy area<br />

- acquired the largest portion accounting for 30 percent of the total electricity consumption.<br />

However, relying on power from other areas, and lacking its own capacity, the area has been<br />

confronted with the challenge of the continuously growing power demand. Therefore,<br />

power plants are needed to be developed to maintain power system reliability in the area<br />

during 2019-2025 as the following:<br />

In 2019, replacement of South Bangkok Thermal <strong>Power</strong> <strong>Plan</strong>t<br />

unit 1-5 1,300 MW<br />

In 2019, replacement of Bang Pakong Thermal <strong>Power</strong> <strong>Plan</strong>t unit 1-2 1,300 MW<br />

In 2022, replacement of South Bangkok Combined Cycle <strong>Power</strong> <strong>Plan</strong>t<br />

unit 1-2 1,300 MW<br />

In 2023, replacement of Wang Noi Combined Cycle <strong>Power</strong> <strong>Plan</strong>t<br />

unit 1-2 1,300 MW<br />

In 2025, replacement of Wang Noi Combined Cycle <strong>Power</strong> <strong>Plan</strong>t<br />

unit 3 1,300 MW<br />

2-5