6.3.3 Transmission System Expansion and Renovation Project, Phase 2<br />

The Transmission System Expansion and Renovation Project, Phase 2, a<br />

successive scheme of Phase 1 involves the renovation and expansion of the existing 19<br />

substations and 11 transmission lines and miscellaneous improvement related to the<br />

transmission system. It was approved by the cabinet on January 15, 2013 and planned to<br />

be completed in 2020.<br />

6.3.4 Transmission System Expansion and Renovation Project (Future<br />

Phases)<br />

The successive phases of Transmission System Expansion and<br />

Renovation Projects involve the renovation and expansion of the existing substations and<br />

transmission lines as well as miscellaneous works related to the transmission system in<br />

the future to prevent the power outage and improve the reliability of the transmission<br />

system. The other phases of Transmission System Expansion and Renovation Projects are<br />

as follows:<br />

6-5<br />

Period<br />

Transmission System Expansion and Renovation Project, Phase 3 2017 - 2021<br />

Transmission System Expansion and Renovation Project, Phase 4 2022 - 2026<br />

6.4 Transmission System <strong>Development</strong> for <strong>Power</strong> Purchase<br />

6.4.1 Transmission System <strong>Development</strong> for <strong>Power</strong> Purchase from<br />

Hongsa Lignite-Fired Thermal <strong>Power</strong> <strong>Plan</strong>t Project<br />

The transmission system project aims to accommodate the power<br />

purchase from Hongsa Lignite - Fired Thermal <strong>Power</strong> <strong>Plan</strong>t Project in Lao PDR which is the<br />

first lignite-fired power plant of the capacity of 3x626 MW for supplying 1,473 MW of<br />

power to <strong>Thailand</strong>. The transmission system project consists of the construction of new<br />

500 kV transmission lines from Thai/Lao border (Nan Province) to 500/230/115 kV Nan<br />

Substation to be connected with 500 kV transmission line to the main system at Mae Moh<br />

3 Substation. It was approved by the cabinet on July 13, 2010 and planned to be<br />

completed in year <strong>2015</strong>.<br />

6.4.2 Transmission System <strong>Development</strong> Project for <strong>Power</strong> Purchase from<br />

IPPs (IPP 2007)<br />

The transmission system project aims to accommodate power purchase<br />

from four IPPs according to the <strong>Power</strong> <strong>Development</strong> <strong>Plan</strong> 2007 – 2021 (PDP 2007), which<br />

was approved by the National Energy Policy Council (NEPC) and the cabinet in June 2007.<br />

The project was approved by the cabinet on June 9, 2009 and it comprises four<br />

transmission system sub-projects as follows: