expansion plan to other areas efficiently. It is planned to be completed during 2016 -<br />

2020.<br />

6.1.4 Transmission System Expansion Projects (the future Phases)<br />

The successive phases of Transmission System Expansion Projects of<br />

TS.12 are also aimed to cope with the increasing demand in the Provincial Area except<br />

Bangkok area and its vicinity in the future. The next phases of Transmission System<br />

Expansion Projects and its implementation period are as follows:<br />

Period<br />

Transmission System Expansion Project No. 13 2019 - 2025<br />

Transmission System Expansion Project No. 14 2026 - 2032<br />

Transmission System Expansion Project No. 15 2033 - 2039<br />

6.2 Transmission System Improvement Project in <strong>Thailand</strong> to Enhance System<br />

Security<br />

6.2.1 Transmission System Improvement Project in Eastern Region to<br />

Enhance System Security<br />

This transmission system project aims to improve the system security in<br />

the eastern region of <strong>Thailand</strong> to continuously cope with the growing electricity demand<br />

and to receive the electric power from new power plants. This project consists of the<br />

constructions of 500 kV and 230 kV transmission systems. It was approved by the Cabinet<br />

on April 23, 2013 and planned to be completed within two phases: by year 2017 and<br />

2019.<br />

6.2.2 Transmission System Improvement Project in Western and Southern<br />

Regions to Enhance System Security<br />

The transmission system improvement project comprises the<br />

construction of the 500 kV transmission system lines and the renovation of 230 kV<br />

transmission systems to cope with the growing electricity demand in the southern part of<br />

<strong>Thailand</strong> in the long term and to increase the capability of the transmission system from<br />

the West/Central of <strong>Thailand</strong> to the South in order to promote the growth of business,<br />

industry and tourism sectors in the southern region especially in Phuket Province<br />

including remedy in the power outage problem in the South. It was approved by the<br />

National Council for Peace and Order (NCPO) on August 19, 2014 and planned to be<br />

completed within two phases: by year 2019 and 2022.<br />