Minimization and Mitigation Measures<br />
Various improvements have been identified to mitigate to the maximum extent practicable the<br />
Project’s potential impact to existing traffic patterns and flows. It is noted that the<br />
improvements typically include traffic signals and turn lanes at intersections. Based on<br />
conversations with NYSDOT, alternative traffic controls, such as roundabouts, shall be<br />
considered, and the intersections shall be monitored to determine when the improvements<br />
should be installed.<br />
Access to the Project Site shall be provided through Crosby Road during Phase 1. It is<br />
recommended that a right-turn lane be constructed on the east bound Judge Road approach of<br />
the NY Route 77/NY Route 63 intersection, and that this intersection and the NY Route<br />
77/Ledge Road intersection be monitored for the potential installation of traffic signals during<br />
Phase 1 of the Project’s development.<br />
After Phase 1, and before the 70% threshold for Project build-out is reached, it is recommended<br />
that a bypass road be constructed through the Project Site from NY Route 77/63 Overlap just<br />
north of Ham Road to NY Route 77 at the existing location of the intersection of Crosby Road.<br />
This connector road will provide access to the Project Site, and will allow through traffic on NY<br />
Route 77 to bypass the Hamlet of Alabama, reducing potential traffic impacts in the Hamlet of<br />
Alabama. Designating the bypass road at Route 77 and de-designating existing NY Route 77<br />
through the Hamlet of Alabama will be considered. In addition to the connector road, several<br />
new site driveways shall be constructed as needed and in correlation to the phased<br />
development of the Project Site. These site access improvements include: two (2) driveways<br />
on NY Route 77; two (2) driveways on Judge Road; and two (2) driveways on NY Route 77/63<br />
Overlap (in addition to the bypass road curb cuts).<br />
Traffic capacity improvements shall be completed (as needed) at several off-site intersections<br />
including:<br />
NY Route 77/NY Route 63/Judge Road<br />
NY Route 77/Bloomingdale Road<br />
NY Route 77/Ledge Road<br />
NY Route 77/Akron Road<br />
NY Route 77/I-90 Exit 48A<br />
The actual timing and necessity of these improvements will be confirmed after completion of<br />
Phase 1 development and subject to the review and approval of NYSDOT.<br />
The full build-out analysis of the Preferred Alternative indicates that a majority of the study<br />
area intersections will continue to operate adequately. A two-lane capacity analysis of NY<br />
Route 77 shows that only the Judge Road to Bloomingdale Road segment may become<br />
congested during full build-out conditions. Since additional mitigation above and beyond the<br />
improvements identified for the 70% threshold may be necessary to provide adequate<br />
operations at a few locations, a supplemental traffic analysis shall be conducted after the 70%<br />