The Project:<br />
Town of Islip - Drainage Improvements Capital (P720)<br />
April 17, 2012<br />
On February 21, 2008, the Directors approved a $250,000 Community Capital Assistance<br />
Program grant (V555) for repairs and renovations of the Homan’s Creek dock. The<br />
project was completed and funds disbursed.<br />
Completion - December 31, 2012<br />
Activity – The grant was intended to improve and upgrade drainage facilities on<br />
Prospect Avenue and Boulevard Avenue to address the flooding of local streets. The<br />
$440,000 grant included an engineering study, and improvement and upgrading of<br />
drainage facilities, including new leaching basins and bubbler systems. In addition,<br />
road improvements will be required.<br />
The Town is now requesting a modification to change the location of the project to<br />
Middlesex Avenue from Grassmere Avenue east, to the east side of Hollywood<br />
Drive. The Town determined that it was necessary to address the flooding issue in<br />
the Middlesex Avenue and Oakland Avenue area first.<br />
Budget – The project budget reflects cost increases since its approval in June 2002. The<br />
revised budget is shown below.<br />
Results – The project as completed will correct the flooding problem in the area,<br />
increasing the number of parking spaces available for residents and will enhance the<br />
area’s quality of life.<br />
Financing Uses Amount Financing Sources Amount Percent<br />
Cost related to the improvement<br />
and upgrade of existing drainage<br />
and road improvements including<br />
pavement.<br />
Grantee Contact - Tom Croci, Town Supervisor<br />
Town Hall<br />
655 Main Street<br />
Islip, NY 11751<br />
Phone: (631) 224-5500<br />
$768,550 ESD Grant $440,000 55%<br />
Contingency 27,000 Town Capital Fund $355,550 45%<br />
Total Project Costs $795,550 Total Project Financing $795,550 100%<br />