Switch management system shows loss of protection warning<br />

Other comments:<br />

None<br />

<strong>Test</strong> <strong>Plan</strong> <strong>for</strong> <strong>Optical</strong> <strong>Grooming</strong> <strong>Switches</strong><br />

TCA016: Confirm mesh restoration is used when working and protection 1+1 MSP<br />

trunks are failed<br />

Purpose:<br />

Confirm mesh restoration is used when working and protection 1+1 MSP trunks are failed<br />

<strong>Test</strong> method:<br />

1. Following on from successful completion of TCA015<br />

2. Pull out card PAR#6<br />

Expected result:<br />

Mesh restoration takes place and routes STS-1 via 2 hop route Par#8-PAR#5-<br />

NY#3-NY#4-LON#4-LON#5<br />

Record duration of loss of traffic on STS-1 circuit<br />

STS-3c circuit should see no loss of traffic<br />

Other comments:<br />

None<br />

TCA017: Confirm support <strong>for</strong> BLSR and mesh restoration on same switch – part A<br />

Purpose:<br />

To confirm same switch can support BLSR and mesh restoration at same time<br />

<strong>Test</strong> method:<br />

1. Start off with “clean” configuration A – no alarms and no circuits configured<br />

2. Set up unprotected STS-1 circuit from LA#8 to NY#6<br />

3. Set up unprotected STS-3c circuit from NY#7 to LON#5<br />

4. Confirm STS-1 circuit is routed via BLSR<br />

5. Identify which LA-NY fibre is the working fibre <strong>for</strong> STS-1 and break the working fibre<br />

Expected result:<br />

BLSR should switch<br />

STS-1 circuit should see sub-50ms traffic loss<br />

STS-3c circuit should see no loss of traffic<br />

Other comments:<br />

None<br />

TCA018: Confirm support <strong>for</strong> BLSR and mesh restoration on same switch – part B<br />

Purpose:<br />

To confirm same switch can support BLSR and mesh restoration at same time<br />

<strong>Test</strong> method:<br />

1. Following on from completion of TCA017<br />

2. Break fibre LON#4-NY#4<br />

Expected result:<br />

STS-1 circuit should be unaffected – no loss of traffic<br />

Switch management system should show LON#4-NY#4 fibre cut<br />

24