Test Plan for Optical Grooming Switches - Light Reading
Test Plan for Optical Grooming Switches - Light Reading
Test Plan for Optical Grooming Switches - Light Reading
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
<strong>Test</strong> <strong>Plan</strong> <strong>for</strong> <strong>Optical</strong> <strong>Grooming</strong> <strong>Switches</strong><br />
Expected result:<br />
Traffic on STS-1 trail should not be affected<br />
Alarm should be raised on switch management system within 10 seconds<br />
indicating card out<br />
Any other comments:<br />
BTexact to select the most suitable card depending on equipment implementation<br />
END OF BLOCK 12<br />
BLOCK 13. Node Failure and 1:N transponder protection on WDM system<br />
<strong>Test</strong> Block description:<br />
Procedure:<br />
Blocks of tests to proceed in sequence from TCA063 to TC065.<br />
TCA063: Node failure and trail restoration<br />
Purpose:<br />
If an entire node is destroyed in a ring network, as many as possible of the circuits passing<br />
through the node should be switched/restored<br />
<strong>Test</strong> method:<br />
1. Start off with “clean” configuration A – no alarms and no trails configured<br />
2. Break fibre PAR#5-NY#3<br />
3. Set up unprotectedSTS-1 trail from PAR#8-NY#6 and monitor traffic over it using<br />
4. Pull out all fuses (one at a time) on London node (assuming 2.5G circuit is routed via<br />
London – if via LA then use LA instead) – thus killing the node<br />
5. Confirm traffic is restored<br />
Expected results:<br />
• Single fuse removal should not be traffic affecting.<br />
• 2.5G Paris-NY circuit should be re-routed. Record the new route and the duration of<br />
any loss of traffic.<br />
• Alarms should be raised to indicate loss of node<br />
Any other comments:<br />
None<br />
TCA064: <strong>Test</strong> reboot of failed node<br />
Purpose:<br />
To see what happens when London node is on again<br />
<strong>Test</strong> method:<br />
1. Follows on from successful completion of TCA063<br />
2. Replace the fuses in London node and wait until the node is up again<br />
3. Monitor and note node rack alarms<br />
4. Monitor and management system and note time period from power on to node appears as<br />
present on management system.<br />
Expected results:<br />
46